If man A complete a work in 10 days & ma...

If man A complete a work in 10 days & man B complete the same work in 15 days , in how many days the work is completed if they work together ?

A

5 days

B

6 days

C

8 days

D

9 days

Text Solution

Verified by Experts

The correct Answer is:
B
Doubtnut Promotions Banner Mobile Dark
|

Topper's Solved these Questions

  • TIME AND WORK

    MAHENDRA|Exercise EXERCISES|25 Videos
  • TEST-9 QUANTITATIVE APTITUDE

    MAHENDRA|Exercise MULTIPLE CHOICE QUESTIONS|50 Videos

Similar Questions

Explore conceptually related problems

A can complete a work in 12 days and B complete the same work in 15 days. Find the time taken by them when A and B worked together.

A and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work ?

Knowledge Check

  • A and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?

    A
    4
    B
    15
    C
    `15/4`
    D
    16
  • Both A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?

    A
    30
    B
    50
    C
    45
    D
    42
  • Both A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?

    A
    30
    B
    50
    C
    45
    D
    42
  • Similar Questions

    Explore conceptually related problems

    A can do a work in x days while B can do the same work in y days then in how many days will they complete the work, working together?

    A alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?

    U, V and W together can complete a work in 15 days. U alone can complete the work in 60 days. In how many days V and W together can complete the same work?

    A alone can complete a work in 10 days and B alone can complete the same work in 20 days. In how many days both 4 and B together can complete half of the total work?

    A alone can complete a work in 6 days and B alone can complete the same work in 8 days. In how many days both A and B together can complete the same work?