A B and C can complete a piece of work in 24, 6 and 12 days respectively. They will complete the same work in :

A

`1/(24) ` days

B

`7/(24)` days

C

` 3 3/7` days

D

4 days

Text Solution

Verified by Experts

The correct Answer is:
C
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    MAHENDRA|Exercise EXERCISES|25 Videos
  • TEST-9 QUANTITATIVE APTITUDE

    MAHENDRA|Exercise MULTIPLE CHOICE QUESTIONS|50 Videos

Similar Questions

Explore conceptually related problems

A and B can do a piece of work in 6 and 12 days, respectively. They (both) will complete the work in how many days?

A, B and C can complete a piece of work in 24, 5 and 12 days respectively. Working together, they will complete the same work in 7/(24)d a y s b. 3 3/7d a y s c. 4 d a y s d. 3 1/(13)d a y s

A, B and C can complete a piec of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work in completed ?

A, B and C can complete a piece of work in 10, 20 and 60 days respectively. Working together they can complete the same work in how many days?

MAHENDRA-TIME AND WORK -EXERCISES
  1. If man A complete a work in 10 days & man B complete the same work in ...

    Text Solution

    |

  2. A B and C can complete a piece of work in 24, 6 and 12 days respective...

    Text Solution

    |

  3. A man can do a job in 15 days. His father takes 20 days and his son fi...

    Text Solution

    |

  4. A man can do a piece of work in 5 days, but with the help of his son h...

    Text Solution

    |

  5. A can lay railway track between two given stations in 16 days and B ca...

    Text Solution

    |

  6. A takes twice as much time as B and thrice as much time as C finish a ...

    Text Solution

    |

  7. Mohan and Sohan are working on a assignment. Mohan takes 6 hours to ty...

    Text Solution

    |

  8. Two workers A and B are engaged to do a piece of work. A working alone...

    Text Solution

    |

  9. P can complete a work in 12 days working 8 hours a day. Q can complete...

    Text Solution

    |

  10. A and B can do a work in 12 days, B and C in 15 days, C and A in 20 da...

    Text Solution

    |

  11. A and B can do a piece of work in 72 days, B and C can do it in 120 da...

    Text Solution

    |

  12. A and B can do a piece of work in 5 days, B and C can do it in 7 days ...

    Text Solution

    |

  13. A can do a piece of work in 4 hours: B and C can do it in 3 hours. A a...

    Text Solution

    |

  14. A can do a certain work in the same time in which B and C together can...

    Text Solution

    |

  15. A Works twice as fast as B. If B can complete a work in 12 days indepe...

    Text Solution

    |

  16. A is 30% more efficient than B. How much time will they, working toget...

    Text Solution

    |

  17. A does half as much work as B in three-fourth of the time. If together...

    Text Solution

    |

  18. A can finish a work in 18 days and B can do the same work in 15 days. ...

    Text Solution

    |

  19. Ram and Mohan can complete a work in 15 days and 10 days respectively....

    Text Solution

    |

  20. A can finish a work in 24 days, B in 9 days and C in 12 days. B and C ...

    Text Solution

    |