Home
Class 14
MATHS
P can complete a work in 12 days working...

P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how man days can they complete the work ?

A

`5 5/(11)`

B

`5 6/(11)`

C

`6 5/(11)`

D

`6 6/(11)`

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's break it down: ### Step 1: Calculate the total work done by P and Q in hours. - P can complete the work in 12 days, working 8 hours a day. - Total hours worked by P = 12 days * 8 hours/day = 96 hours. - Q can complete the work in 8 days, working 10 hours a day. - Total hours worked by Q = 8 days * 10 hours/day = 80 hours. ### Step 2: Determine the work done by P and Q in one hour. - Work done by P in one hour = 1/96 (since he completes the work in 96 hours). - Work done by Q in one hour = 1/80 (since he completes the work in 80 hours). ### Step 3: Calculate the combined work done by P and Q in one hour. - Combined work done by P and Q in one hour = (1/96 + 1/80). - To add these fractions, we need a common denominator. The least common multiple (LCM) of 96 and 80 is 480. Calculating the fractions: - Work done by P in one hour = 1/96 = 5/480. - Work done by Q in one hour = 1/80 = 6/480. Now, adding these: - Combined work = (5/480 + 6/480) = 11/480. ### Step 4: Calculate the total time taken to complete the work when they work together for 8 hours a day. - In one hour, P and Q together complete 11/480 of the work. - In 8 hours, they complete: \[ 8 \times \frac{11}{480} = \frac{88}{480} = \frac{11}{60} \text{ of the work.} \] ### Step 5: Calculate the total days required to complete the work. - To find out how many days it will take to complete the entire work (1 unit of work), we set up the equation: \[ \text{Total days} = \frac{1 \text{ (total work)}}{\frac{11}{60} \text{ (work done in one day)}} \] \[ \text{Total days} = \frac{60}{11} \text{ days.} \] ### Step 6: Convert the total days into mixed fraction. - Dividing 60 by 11 gives us 5 with a remainder of 5. - Therefore, the answer in mixed fraction form is: \[ 5 \frac{5}{11} \text{ days.} \] ### Final Answer: P and Q can complete the work together in \( \frac{60}{11} \) days or \( 5 \frac{5}{11} \) days. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    MAHENDRA|Exercise EXERCISES|25 Videos
  • TEST-9 QUANTITATIVE APTITUDE

    MAHENDRA|Exercise MULTIPLE CHOICE QUESTIONS|50 Videos
MAHENDRA-TIME AND WORK -EXERCISES
  1. A takes twice as much time as B and thrice as much time as C finish a ...

    Text Solution

    |

  2. Mohan and Sohan are working on a assignment. Mohan takes 6 hours to ty...

    Text Solution

    |

  3. Two workers A and B are engaged to do a piece of work. A working alone...

    Text Solution

    |

  4. P can complete a work in 12 days working 8 hours a day. Q can complete...

    Text Solution

    |

  5. A and B can do a work in 12 days, B and C in 15 days, C and A in 20 da...

    Text Solution

    |

  6. A and B can do a piece of work in 72 days, B and C can do it in 120 da...

    Text Solution

    |

  7. A and B can do a piece of work in 5 days, B and C can do it in 7 days ...

    Text Solution

    |

  8. A can do a piece of work in 4 hours: B and C can do it in 3 hours. A a...

    Text Solution

    |

  9. A can do a certain work in the same time in which B and C together can...

    Text Solution

    |

  10. A Works twice as fast as B. If B can complete a work in 12 days indepe...

    Text Solution

    |

  11. A is 30% more efficient than B. How much time will they, working toget...

    Text Solution

    |

  12. A does half as much work as B in three-fourth of the time. If together...

    Text Solution

    |

  13. A can finish a work in 18 days and B can do the same work in 15 days. ...

    Text Solution

    |

  14. Ram and Mohan can complete a work in 15 days and 10 days respectively....

    Text Solution

    |

  15. A can finish a work in 24 days, B in 9 days and C in 12 days. B and C ...

    Text Solution

    |

  16. Machine P can print one lakh books in 8 hours, machine Q can print the...

    Text Solution

    |

  17. A and B can do a piece of work in 30 days while B and C can do the sam...

    Text Solution

    |

  18. X and Y can do a piece of work in 20 days and 12 days respectively. X ...

    Text Solution

    |

  19. X can do a piece of work in 40 days. He works it for 8 days and then ...

    Text Solution

    |

  20. If 5 men or 9 women can do a piece of work in 19 days. 3 men and 6 wom...

    Text Solution

    |