A is 30% more efficient than B. How much time will they, working together, take complete a job which A alone could have done in 23 days?

A

11 days .

B

13 days

C

`20 3/(17)` days

D

15 days

Text Solution

Verified by Experts

The correct Answer is:
B
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    MAHENDRA|Exercise EXERCISES|25 Videos
  • TEST-9 QUANTITATIVE APTITUDE

    MAHENDRA|Exercise MULTIPLE CHOICE QUESTIONS|50 Videos

Similar Questions

Explore conceptually related problems

A is 30% more efficient than B .How much time will they,working together,take to complete a job which A alone could have done in 23 days? a.11 days b.13 days c.20(3)/(17) days d.none of these

Anand is 50% more efficient than Bharath and Bharath is 100% more efficient that Chandu. Working together, they can complete a work in 10 days. In how many days can Anand alone do the work?

A is 20% more efficient than B. If B alone can complete a piece of work in 12 days, then A alone can complete the same work in how many days?

MAHENDRA-TIME AND WORK -EXERCISES
  1. A takes twice as much time as B and thrice as much time as C finish a ...

    Text Solution

    |

  2. Mohan and Sohan are working on a assignment. Mohan takes 6 hours to ty...

    Text Solution

    |

  3. Two workers A and B are engaged to do a piece of work. A working alone...

    Text Solution

    |

  4. P can complete a work in 12 days working 8 hours a day. Q can complete...

    Text Solution

    |

  5. A and B can do a work in 12 days, B and C in 15 days, C and A in 20 da...

    Text Solution

    |

  6. A and B can do a piece of work in 72 days, B and C can do it in 120 da...

    Text Solution

    |

  7. A and B can do a piece of work in 5 days, B and C can do it in 7 days ...

    Text Solution

    |

  8. A can do a piece of work in 4 hours: B and C can do it in 3 hours. A a...

    Text Solution

    |

  9. A can do a certain work in the same time in which B and C together can...

    Text Solution

    |

  10. A Works twice as fast as B. If B can complete a work in 12 days indepe...

    Text Solution

    |

  11. A is 30% more efficient than B. How much time will they, working toget...

    Text Solution

    |

  12. A does half as much work as B in three-fourth of the time. If together...

    Text Solution

    |

  13. A can finish a work in 18 days and B can do the same work in 15 days. ...

    Text Solution

    |

  14. Ram and Mohan can complete a work in 15 days and 10 days respectively....

    Text Solution

    |

  15. A can finish a work in 24 days, B in 9 days and C in 12 days. B and C ...

    Text Solution

    |

  16. Machine P can print one lakh books in 8 hours, machine Q can print the...

    Text Solution

    |

  17. A and B can do a piece of work in 30 days while B and C can do the sam...

    Text Solution

    |

  18. X and Y can do a piece of work in 20 days and 12 days respectively. X ...

    Text Solution

    |

  19. X can do a piece of work in 40 days. He works it for 8 days and then ...

    Text Solution

    |

  20. If 5 men or 9 women can do a piece of work in 19 days. 3 men and 6 wom...

    Text Solution

    |