Machine P can print one lakh books in 8 ...

Machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print the same number of books in 12 hours. All the machines are started at 9 a.m. while machine P is closed at 11 a.m. and the remaining two machines complete the work. Approximately at what time will the work be finished ?

A

`11:30` AM

B

12 noon

C

12 :30 p.m.

D

1 p.m.

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will calculate the work done by each machine, the total work, and the time taken to complete the work. ### Step 1: Determine the work done by each machine per hour - Machine P can print 1 lakh books in 8 hours. - Work done by P in 1 hour = 100000 books / 8 hours = 12500 books/hour - Machine Q can print 1 lakh books in 10 hours. - Work done by Q in 1 hour = 100000 books / 10 hours = 10000 books/hour - Machine R can print 1 lakh books in 12 hours. - Work done by R in 1 hour = 100000 books / 12 hours = 8333.33 books/hour (approximately) ### Step 2: Calculate the combined work done by all machines in the first 2 hours - All machines work together from 9 a.m. to 11 a.m. (2 hours). - Combined work done in 1 hour = Work done by P + Work done by Q + Work done by R - Combined work done in 1 hour = 12500 + 10000 + 8333.33 = 30833.33 books/hour - Work done in 2 hours = 30833.33 books/hour * 2 hours = 61666.67 books ### Step 3: Calculate the remaining work - Total work = 100000 books - Work done in 2 hours = 61666.67 books - Remaining work = Total work - Work done in 2 hours - Remaining work = 100000 - 61666.67 = 38333.33 books ### Step 4: Calculate the work done by machines Q and R after P is closed - After 11 a.m., only machines Q and R are working. - Combined work done by Q and R in 1 hour = Work done by Q + Work done by R - Combined work done by Q and R = 10000 + 8333.33 = 18333.33 books/hour ### Step 5: Calculate the time taken to finish the remaining work - Time taken to finish remaining work = Remaining work / Combined work done by Q and R - Time = 38333.33 books / 18333.33 books/hour ≈ 2.09 hours ### Step 6: Calculate the finishing time - 2.09 hours is approximately 2 hours and 5 minutes. - Since the remaining work starts at 11 a.m., we add 2 hours and 5 minutes to 11 a.m. - Finishing time = 11:00 a.m. + 2 hours 5 minutes = 1:05 p.m. ### Conclusion The work will be finished approximately at **1:05 p.m.**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    MAHENDRA|Exercise EXERCISES|25 Videos
  • TEST-9 QUANTITATIVE APTITUDE

    MAHENDRA|Exercise MULTIPLE CHOICE QUESTIONS|50 Videos
MAHENDRA-TIME AND WORK -EXERCISES
  1. A takes twice as much time as B and thrice as much time as C finish a ...

    Text Solution

    |

  2. Mohan and Sohan are working on a assignment. Mohan takes 6 hours to ty...

    Text Solution

    |

  3. Two workers A and B are engaged to do a piece of work. A working alone...

    Text Solution

    |

  4. P can complete a work in 12 days working 8 hours a day. Q can complete...

    Text Solution

    |

  5. A and B can do a work in 12 days, B and C in 15 days, C and A in 20 da...

    Text Solution

    |

  6. A and B can do a piece of work in 72 days, B and C can do it in 120 da...

    Text Solution

    |

  7. A and B can do a piece of work in 5 days, B and C can do it in 7 days ...

    Text Solution

    |

  8. A can do a piece of work in 4 hours: B and C can do it in 3 hours. A a...

    Text Solution

    |

  9. A can do a certain work in the same time in which B and C together can...

    Text Solution

    |

  10. A Works twice as fast as B. If B can complete a work in 12 days indepe...

    Text Solution

    |

  11. A is 30% more efficient than B. How much time will they, working toget...

    Text Solution

    |

  12. A does half as much work as B in three-fourth of the time. If together...

    Text Solution

    |

  13. A can finish a work in 18 days and B can do the same work in 15 days. ...

    Text Solution

    |

  14. Ram and Mohan can complete a work in 15 days and 10 days respectively....

    Text Solution

    |

  15. A can finish a work in 24 days, B in 9 days and C in 12 days. B and C ...

    Text Solution

    |

  16. Machine P can print one lakh books in 8 hours, machine Q can print the...

    Text Solution

    |

  17. A and B can do a piece of work in 30 days while B and C can do the sam...

    Text Solution

    |

  18. X and Y can do a piece of work in 20 days and 12 days respectively. X ...

    Text Solution

    |

  19. X can do a piece of work in 40 days. He works it for 8 days and then ...

    Text Solution

    |

  20. If 5 men or 9 women can do a piece of work in 19 days. 3 men and 6 wom...

    Text Solution

    |