Home
Class 14
MATHS
X and Y can do a piece of work in 20 day...

X and Y can do a piece of work in 20 days and 12 days respectively. X started line work alone and then after 4 days Y joined him till the completion of the work. How long did the work last ?

A

6 days

B

10 days

C

30 days

D

36 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will calculate how long the work lasted when X and Y worked together. ### Step 1: Determine the total work The total work can be calculated based on the time taken by X and Y to complete the work individually. - X can complete the work in 20 days. - Y can complete the work in 12 days. To find the total work in terms of units, we can take the least common multiple (LCM) of their individual work times. **Total Work (TW) = LCM(20, 12)** Calculating the LCM: - The prime factorization of 20 is \(2^2 \times 5^1\). - The prime factorization of 12 is \(2^2 \times 3^1\). The LCM is found by taking the highest power of each prime: - LCM = \(2^2 \times 3^1 \times 5^1 = 60\) So, the total work is **60 units**. ### Step 2: Calculate the efficiency of X and Y Next, we calculate the efficiency (work done per day) of X and Y. - Efficiency of X = Total Work / Days taken by X = \(60 / 20 = 3\) units per day. - Efficiency of Y = Total Work / Days taken by Y = \(60 / 12 = 5\) units per day. ### Step 3: Calculate the work done by X in the first 4 days Since X starts the work alone for the first 4 days, we can calculate how much work he completes in that time. - Work done by X in 4 days = Efficiency of X × Number of days = \(3 \times 4 = 12\) units. ### Step 4: Calculate the remaining work Now, we find out how much work is left after X has worked alone for 4 days. - Remaining work = Total Work - Work done by X = \(60 - 12 = 48\) units. ### Step 5: Calculate the time taken by X and Y to complete the remaining work Now that both X and Y are working together, we can calculate how much work they can do together in one day. - Combined efficiency of X and Y = Efficiency of X + Efficiency of Y = \(3 + 5 = 8\) units per day. Now, we can find out how many days it will take for them to complete the remaining work. - Time taken to complete remaining work = Remaining work / Combined efficiency = \(48 / 8 = 6\) days. ### Step 6: Calculate the total time of work Finally, we add the time X worked alone to the time taken by both X and Y to complete the remaining work. - Total time of work = Time worked by X alone + Time worked by X and Y together = \(4 + 6 = 10\) days. Thus, the total duration of the work is **10 days**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    MAHENDRA|Exercise EXERCISES|25 Videos
  • TEST-9 QUANTITATIVE APTITUDE

    MAHENDRA|Exercise MULTIPLE CHOICE QUESTIONS|50 Videos
MAHENDRA-TIME AND WORK -EXERCISES
  1. A takes twice as much time as B and thrice as much time as C finish a ...

    Text Solution

    |

  2. Mohan and Sohan are working on a assignment. Mohan takes 6 hours to ty...

    Text Solution

    |

  3. Two workers A and B are engaged to do a piece of work. A working alone...

    Text Solution

    |

  4. P can complete a work in 12 days working 8 hours a day. Q can complete...

    Text Solution

    |

  5. A and B can do a work in 12 days, B and C in 15 days, C and A in 20 da...

    Text Solution

    |

  6. A and B can do a piece of work in 72 days, B and C can do it in 120 da...

    Text Solution

    |

  7. A and B can do a piece of work in 5 days, B and C can do it in 7 days ...

    Text Solution

    |

  8. A can do a piece of work in 4 hours: B and C can do it in 3 hours. A a...

    Text Solution

    |

  9. A can do a certain work in the same time in which B and C together can...

    Text Solution

    |

  10. A Works twice as fast as B. If B can complete a work in 12 days indepe...

    Text Solution

    |

  11. A is 30% more efficient than B. How much time will they, working toget...

    Text Solution

    |

  12. A does half as much work as B in three-fourth of the time. If together...

    Text Solution

    |

  13. A can finish a work in 18 days and B can do the same work in 15 days. ...

    Text Solution

    |

  14. Ram and Mohan can complete a work in 15 days and 10 days respectively....

    Text Solution

    |

  15. A can finish a work in 24 days, B in 9 days and C in 12 days. B and C ...

    Text Solution

    |

  16. Machine P can print one lakh books in 8 hours, machine Q can print the...

    Text Solution

    |

  17. A and B can do a piece of work in 30 days while B and C can do the sam...

    Text Solution

    |

  18. X and Y can do a piece of work in 20 days and 12 days respectively. X ...

    Text Solution

    |

  19. X can do a piece of work in 40 days. He works it for 8 days and then ...

    Text Solution

    |

  20. If 5 men or 9 women can do a piece of work in 19 days. 3 men and 6 wom...

    Text Solution

    |