Home
Class 14
MATHS
There are three pipes-A, B & C. A & B ar...

There are three pipes-A, B & C. A & B are filling pipes and C is emptying pipe. Pipe-A alone can fill the tank in 1 hours & pipe-C is 20% more efficient than pipe. A If pipe-A & B working together fill the tank in `(75)/(2)` minutes. Then find in how much time pipe. A B & C working together can fill the tank?

A

6 hours

B

4.5 hours

C

2.5 hours

D

3 hours

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's break it down: ### Step 1: Understand the efficiencies of pipes A and C - Pipe A can fill the tank in 1 hour, which means its efficiency is: \[ \text{Efficiency of A} = \frac{1 \text{ tank}}{1 \text{ hour}} = 1 \text{ tank/hour} \] - Since pipe C is 20% more efficient than pipe A, we calculate the efficiency of pipe C: \[ \text{Efficiency of C} = 1 \text{ tank/hour} + 0.2 \times 1 \text{ tank/hour} = 1.2 \text{ tanks/hour} \] ### Step 2: Convert the time taken by A and B to fill the tank together - Pipe A and B together fill the tank in \( \frac{75}{2} \) minutes. We convert this to hours: \[ \frac{75}{2} \text{ minutes} = \frac{75}{120} \text{ hours} = \frac{5}{8} \text{ hours} \] ### Step 3: Calculate the combined efficiency of pipes A and B - The total work done (filling one tank) can be expressed as: \[ \text{Efficiency of A + B} = \frac{1 \text{ tank}}{\frac{5}{8} \text{ hours}} = \frac{8}{5} \text{ tanks/hour} \] ### Step 4: Find the efficiency of pipe B - We know the efficiency of pipe A is 1 tank/hour. Therefore, the efficiency of pipe B can be calculated as: \[ \text{Efficiency of B} = \text{Efficiency of A + B} - \text{Efficiency of A} = \frac{8}{5} - 1 = \frac{8}{5} - \frac{5}{5} = \frac{3}{5} \text{ tanks/hour} \] ### Step 5: Calculate the total efficiency of pipes A, B, and C together - The total efficiency of A, B, and C is: \[ \text{Total Efficiency} = \text{Efficiency of A} + \text{Efficiency of B} - \text{Efficiency of C} \] Substituting the values: \[ \text{Total Efficiency} = 1 + \frac{3}{5} - 1.2 = 1 + 0.6 - 1.2 = 0.4 \text{ tanks/hour} \] ### Step 6: Calculate the time taken by A, B, and C together to fill the tank - The time taken to fill the tank when all three pipes are working together is: \[ \text{Time} = \frac{1 \text{ tank}}{\text{Total Efficiency}} = \frac{1}{0.4} = 2.5 \text{ hours} \] ### Final Answer Thus, the time taken by pipes A, B, and C working together to fill the tank is **2.5 hours**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise MAINS QUESTIONS |55 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PREVIOUS YEAR QUESTIONS |32 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PRELIMS QUESTIONS (LEVEL - 1) |40 Videos
  • SPEED, TIME AND DISTANCE

    ADDA247|Exercise Previous Year Questions|31 Videos
ADDA247-TIME AND WORK & PIPE AND CISTERN -PRELIMS QUESTIONS (LEVEL - 2)
  1. Shubham work for 5 days and remaining work was completed by Harvinder ...

    Text Solution

    |

  2. A pipe can fill a tank in 36 minutes & another pipe can-fill it in 48 ...

    Text Solution

    |

  3. There are three pipes-A, B & C. A & B are filling pipes and C is empty...

    Text Solution

    |

  4. If Hemant works for 20 days and Manoj works for 15 days then (3)/(5)th...

    Text Solution

    |

  5. Four men and four women can complete a piece of work in 5 days, while ...

    Text Solution

    |

  6. A & B together can finish a certain piece of work in 6 days. If A redu...

    Text Solution

    |

  7. Efficiency of B is 40% more than efficiency of A and efficiency of C i...

    Text Solution

    |

  8. Pipe P(1) can fill 3//5th of the tank in 9 minutes. There are two more...

    Text Solution

    |

  9. Anurag can complete a piece of work in 280 days and Rohit is 33(1)/(3)...

    Text Solution

    |

  10. If 'a' number of males can do a work in (2a-8) days while (a-8) number...

    Text Solution

    |

  11. 8 men and 10 women can do a work in 15 days while 10 men and 18 women ...

    Text Solution

    |

  12. A, B & C are three inlet pipes. Time taken by A & B together to fill h...

    Text Solution

    |

  13. A & B can complete a work in 24 days and 36 days respectively. A & B t...

    Text Solution

    |

  14. A, B & C working together can complete a work in 18 days and A & C wor...

    Text Solution

    |

  15. A working alone & B working alone can complete a piece of work in 15 d...

    Text Solution

    |

  16. Veer is 20% more efficient than Anurag and Sameer is 33(1)/(3)% less e...

    Text Solution

    |

  17. Pipe-B & D are inlet pipes and pipe-A & C are outlet pipes. Pipe-B & D...

    Text Solution

    |

  18. Manish and Suresh can do a task A in 48 days and 60 days respectively....

    Text Solution

    |

  19. P can do a work in ((1)/(4))^(th) of time in which Q alone can do and ...

    Text Solution

    |

  20. P alone and Q alone can do a piece of work in x and (3x)/(2) days resp...

    Text Solution

    |