Home
Class 14
MATHS
If 'a' number of males can do a work in ...

If 'a' number of males can do a work in (2a-8) days while (a-8) number of males can do that work in (2a + 12) days, then find in how many days `(3)/(2)`a number of males can do `33(1)/(3)%` of that work?

A

12 days

B

`8(8)/(9)` days

C

`6(2)/(3)` days

D

8 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's break it down: ### Step 1: Determine the total work done We know that the total work can be calculated using the formula: \[ \text{Total Work} = \text{Number of Workers} \times \text{Days Taken} \] From the first condition, we have: - Number of males = \( a \) - Days = \( 2a - 8 \) Thus, the total work from the first condition is: \[ \text{Total Work} = a \times (2a - 8) = 2a^2 - 8a \] From the second condition, we have: - Number of males = \( a - 8 \) - Days = \( 2a + 12 \) Thus, the total work from the second condition is: \[ \text{Total Work} = (a - 8) \times (2a + 12) = 2a^2 + 12a - 16a - 96 = 2a^2 - 4a - 96 \] ### Step 2: Equate the two expressions for total work Since both expressions represent the same total work, we can set them equal to each other: \[ 2a^2 - 8a = 2a^2 - 4a - 96 \] ### Step 3: Simplify the equation Cancelling \( 2a^2 \) from both sides gives: \[ -8a = -4a - 96 \] Now, rearranging the equation: \[ -8a + 4a = -96 \] \[ -4a = -96 \] \[ a = 24 \] ### Step 4: Calculate the total work Substituting \( a = 24 \) back into the total work formula: \[ \text{Total Work} = a \times (2a - 8) = 24 \times (2 \times 24 - 8) \] \[ = 24 \times (48 - 8) = 24 \times 40 = 960 \] ### Step 5: Determine the work needed We need to find out how much work \( \frac{1}{3} \) of \( 33 \frac{1}{3}\% \) of the total work is: \[ 33 \frac{1}{3}\% = \frac{33.33}{100} = \frac{1}{3} \] So, \( \frac{1}{3} \) of the total work is: \[ \text{Work Needed} = \frac{1}{3} \times 960 = 320 \] ### Step 6: Calculate the efficiency of \( \frac{3}{2} a \) males The number of males is: \[ \frac{3}{2} a = \frac{3}{2} \times 24 = 36 \] ### Step 7: Calculate the time taken to complete the work The efficiency of one male is considered as 1 unit of work per day. Therefore, the total efficiency of 36 males is: \[ \text{Total Efficiency} = 36 \] Now, the time taken to complete 320 units of work is given by: \[ \text{Time} = \frac{\text{Total Work}}{\text{Efficiency}} = \frac{320}{36} = \frac{80}{9} \] ### Step 8: Convert to mixed fraction To express \( \frac{80}{9} \) as a mixed fraction: \[ \frac{80}{9} = 8 \frac{8}{9} \] ### Final Answer Thus, the time taken by \( \frac{3}{2} a \) males to do \( 33 \frac{1}{3}\% \) of the work is: **8 \( \frac{8}{9} \) days**
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise MAINS QUESTIONS |55 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PREVIOUS YEAR QUESTIONS |32 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PRELIMS QUESTIONS (LEVEL - 1) |40 Videos
  • SPEED, TIME AND DISTANCE

    ADDA247|Exercise Previous Year Questions|31 Videos
ADDA247-TIME AND WORK & PIPE AND CISTERN -PRELIMS QUESTIONS (LEVEL - 2)
  1. Pipe P(1) can fill 3//5th of the tank in 9 minutes. There are two more...

    Text Solution

    |

  2. Anurag can complete a piece of work in 280 days and Rohit is 33(1)/(3)...

    Text Solution

    |

  3. If 'a' number of males can do a work in (2a-8) days while (a-8) number...

    Text Solution

    |

  4. 8 men and 10 women can do a work in 15 days while 10 men and 18 women ...

    Text Solution

    |

  5. A, B & C are three inlet pipes. Time taken by A & B together to fill h...

    Text Solution

    |

  6. A & B can complete a work in 24 days and 36 days respectively. A & B t...

    Text Solution

    |

  7. A, B & C working together can complete a work in 18 days and A & C wor...

    Text Solution

    |

  8. A working alone & B working alone can complete a piece of work in 15 d...

    Text Solution

    |

  9. Veer is 20% more efficient than Anurag and Sameer is 33(1)/(3)% less e...

    Text Solution

    |

  10. Pipe-B & D are inlet pipes and pipe-A & C are outlet pipes. Pipe-B & D...

    Text Solution

    |

  11. Manish and Suresh can do a task A in 48 days and 60 days respectively....

    Text Solution

    |

  12. P can do a work in ((1)/(4))^(th) of time in which Q alone can do and ...

    Text Solution

    |

  13. P alone and Q alone can do a piece of work in x and (3x)/(2) days resp...

    Text Solution

    |

  14. Anurag is 40% more efficient than Ayush. Ayush, Anurag and Shivam work...

    Text Solution

    |

  15. Neha who is 50% more efficient than Ritu who take double time than Pri...

    Text Solution

    |

  16. A, B and C can do a piece of work in 20 days, 10 days and 15 days resp...

    Text Solution

    |

  17. Working efficiency of 'A' is twice than that of 'B'.'A' and 'B' togeth...

    Text Solution

    |

  18. 7 men and 6 women together can complete a piece of work in 8 days and ...

    Text Solution

    |

  19. Deepak is 30% less efficient than Dharam and Dharam take 9 days less t...

    Text Solution

    |

  20. B is 40% less efficient than A and efficiency of C is (1)/(4)th the ef...

    Text Solution

    |