Home
Class 14
MATHS
8 men and 10 women can do a work in 15 d...

8 men and 10 women can do a work in 15 days while 10 men and 18 women can do that work in 10 days. 4 men and 5 women started the work and after 10 days all men left the work then find how many more women would be required to complete the whole work in 21 days?

A

12

B

15

C

16

D

10

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's break it down: ### Step 1: Determine the total work done in terms of men and women. Given: - 8 men and 10 women can complete the work in 15 days. - 10 men and 18 women can complete the work in 10 days. **Total work (W)** can be calculated using the formula: \[ W = \text{(Number of workers)} \times \text{(Days)} \] From the first condition: \[ W = (8M + 10W) \times 15 \] From the second condition: \[ W = (10M + 18W) \times 10 \] ### Step 2: Set the equations equal to each other. Since both expressions equal the total work, we can set them equal: \[ (8M + 10W) \times 15 = (10M + 18W) \times 10 \] ### Step 3: Expand and simplify the equation. Expanding both sides: \[ 120M + 150W = 100M + 180W \] Rearranging gives: \[ 120M - 100M = 180W - 150W \] \[ 20M = 30W \] ### Step 4: Find the ratio of men to women. Dividing both sides by 10: \[ 2M = 3W \] Thus, the ratio of men to women is: \[ \frac{M}{W} = \frac{3}{2} \] ### Step 5: Calculate the total work in terms of one variable. Let's express the total work in terms of women (W): Using the first equation: \[ W = (8M + 10W) \times 15 \] Substituting \( M = \frac{2}{3}W \): \[ W = \left(8 \times \frac{2}{3}W + 10W\right) \times 15 \] \[ W = \left(\frac{16}{3}W + 10W\right) \times 15 \] \[ W = \left(\frac{16 + 30}{3}W\right) \times 15 \] \[ W = \left(\frac{46}{3}W\right) \times 15 \] \[ W = 230W \] ### Step 6: Calculate the work done by 4 men and 5 women in 10 days. Using the ratio of work done: - Work done by 4 men in 10 days: \[ \text{Work by 4 men} = 4M \times 10 = 4 \times \frac{2}{3}W \times 10 = \frac{80}{3}W \] - Work done by 5 women in 10 days: \[ \text{Work by 5 women} = 5W \times 10 = 50W \] Total work done in 10 days: \[ \text{Total Work Done} = \frac{80}{3}W + 50W = \frac{80 + 150}{3}W = \frac{230}{3}W \] ### Step 7: Calculate remaining work. Total work is \( 230W \), and work done is \( \frac{230}{3}W \): Remaining work: \[ \text{Remaining Work} = 230W - \frac{230}{3}W = \frac{690 - 230}{3}W = \frac{460}{3}W \] ### Step 8: Determine how many days remain. Total days = 21, days already worked = 10, so remaining days = 11. ### Step 9: Calculate the efficiency required to complete the remaining work. Let \( x \) be the number of women required to complete the remaining work: \[ xW \times 11 = \frac{460}{3}W \] Dividing both sides by \( W \): \[ 11x = \frac{460}{3} \] \[ x = \frac{460}{33} \approx 13.94 \] ### Step 10: Determine how many more women are needed. Initially, there were 5 women working: \[ \text{More women needed} = x - 5 = 13.94 - 5 \approx 8.94 \] Since we need whole women, we round up to 9. ### Conclusion To complete the work in 21 days, **9 more women** are required.
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise MAINS QUESTIONS |55 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PREVIOUS YEAR QUESTIONS |32 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PRELIMS QUESTIONS (LEVEL - 1) |40 Videos
  • SPEED, TIME AND DISTANCE

    ADDA247|Exercise Previous Year Questions|31 Videos
ADDA247-TIME AND WORK & PIPE AND CISTERN -PRELIMS QUESTIONS (LEVEL - 2)
  1. Anurag can complete a piece of work in 280 days and Rohit is 33(1)/(3)...

    Text Solution

    |

  2. If 'a' number of males can do a work in (2a-8) days while (a-8) number...

    Text Solution

    |

  3. 8 men and 10 women can do a work in 15 days while 10 men and 18 women ...

    Text Solution

    |

  4. A, B & C are three inlet pipes. Time taken by A & B together to fill h...

    Text Solution

    |

  5. A & B can complete a work in 24 days and 36 days respectively. A & B t...

    Text Solution

    |

  6. A, B & C working together can complete a work in 18 days and A & C wor...

    Text Solution

    |

  7. A working alone & B working alone can complete a piece of work in 15 d...

    Text Solution

    |

  8. Veer is 20% more efficient than Anurag and Sameer is 33(1)/(3)% less e...

    Text Solution

    |

  9. Pipe-B & D are inlet pipes and pipe-A & C are outlet pipes. Pipe-B & D...

    Text Solution

    |

  10. Manish and Suresh can do a task A in 48 days and 60 days respectively....

    Text Solution

    |

  11. P can do a work in ((1)/(4))^(th) of time in which Q alone can do and ...

    Text Solution

    |

  12. P alone and Q alone can do a piece of work in x and (3x)/(2) days resp...

    Text Solution

    |

  13. Anurag is 40% more efficient than Ayush. Ayush, Anurag and Shivam work...

    Text Solution

    |

  14. Neha who is 50% more efficient than Ritu who take double time than Pri...

    Text Solution

    |

  15. A, B and C can do a piece of work in 20 days, 10 days and 15 days resp...

    Text Solution

    |

  16. Working efficiency of 'A' is twice than that of 'B'.'A' and 'B' togeth...

    Text Solution

    |

  17. 7 men and 6 women together can complete a piece of work in 8 days and ...

    Text Solution

    |

  18. Deepak is 30% less efficient than Dharam and Dharam take 9 days less t...

    Text Solution

    |

  19. B is 40% less efficient than A and efficiency of C is (1)/(4)th the ef...

    Text Solution

    |

  20. If pipe A alone and Pipe B alone can fill a tank in 20 min and 30 min ...

    Text Solution

    |