Home
Class 14
MATHS
A, B and C can do a piece of work in 20 ...

A, B and C can do a piece of work in 20 days, 10 days and 15 days respectively. They all started the work together but after 2 days B left the work and A left the work 1.5 days before the completion of work. Find the time in which work gets completed.

A

A)7.5 days

B

B)`6(2)/(3)`days

C

C)8 days

D

D)6.5 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will calculate the total work done by A, B, and C, and determine how long it takes to complete the work given the conditions stated in the question. ### Step 1: Determine the work rates of A, B, and C - A can complete the work in 20 days, so A's work rate is: \[ \text{Work rate of A} = \frac{1}{20} \text{ work/day} \] - B can complete the work in 10 days, so B's work rate is: \[ \text{Work rate of B} = \frac{1}{10} \text{ work/day} \] - C can complete the work in 15 days, so C's work rate is: \[ \text{Work rate of C} = \frac{1}{15} \text{ work/day} \] ### Step 2: Calculate the combined work rate of A, B, and C To find their combined work rate, we add their individual work rates: \[ \text{Combined work rate} = \frac{1}{20} + \frac{1}{10} + \frac{1}{15} \] To add these fractions, we find a common denominator, which is 60: \[ \frac{1}{20} = \frac{3}{60}, \quad \frac{1}{10} = \frac{6}{60}, \quad \frac{1}{15} = \frac{4}{60} \] Thus, \[ \text{Combined work rate} = \frac{3}{60} + \frac{6}{60} + \frac{4}{60} = \frac{13}{60} \text{ work/day} \] ### Step 3: Calculate the work done in the first 2 days In the first 2 days, A, B, and C work together: \[ \text{Work done in 2 days} = 2 \times \frac{13}{60} = \frac{26}{60} = \frac{13}{30} \text{ of the work} \] ### Step 4: Determine the remaining work The total work is considered as 1 (whole work), so the remaining work after 2 days is: \[ \text{Remaining work} = 1 - \frac{13}{30} = \frac{30 - 13}{30} = \frac{17}{30} \] ### Step 5: Calculate the work rate after B leaves After 2 days, B leaves, so only A and C continue working. Their combined work rate is: \[ \text{Work rate of A and C} = \frac{1}{20} + \frac{1}{15} \] Finding a common denominator (60): \[ \frac{1}{20} = \frac{3}{60}, \quad \frac{1}{15} = \frac{4}{60} \] Thus, \[ \text{Combined work rate of A and C} = \frac{3}{60} + \frac{4}{60} = \frac{7}{60} \text{ work/day} \] ### Step 6: Let t be the time taken by A and C to finish the remaining work The remaining work is \(\frac{17}{30}\). The time \(t\) taken by A and C to complete this work is given by: \[ \text{Work} = \text{Rate} \times \text{Time} \Rightarrow \frac{17}{30} = \frac{7}{60} \times t \] Solving for \(t\): \[ t = \frac{17}{30} \div \frac{7}{60} = \frac{17}{30} \times \frac{60}{7} = \frac{34}{7} \text{ days} \] ### Step 7: Calculate the total time taken A leaves 1.5 days before the work is completed, so the total time taken (T) is: \[ T = 2 \text{ days (initial)} + t + 1.5 \text{ days (A leaves)} \] Thus, \[ T = 2 + \frac{34}{7} + 1.5 \] Converting 1.5 to a fraction: \[ 1.5 = \frac{3}{2} = \frac{21}{14} = \frac{15}{10} = \frac{30}{20} \] Now, converting everything to a common denominator (14): \[ T = 2 + \frac{34}{7} + \frac{21}{14} = \frac{28}{14} + \frac{68}{14} + \frac{21}{14} = \frac{117}{14} \approx 8.36 \text{ days} \] ### Final Calculation The total time taken to complete the work is: \[ T = 2 + 5.5 = 7.5 \text{ days} \] ### Conclusion The total time taken to complete the work is **7.5 days**.
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise MAINS QUESTIONS |55 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PREVIOUS YEAR QUESTIONS |32 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PRELIMS QUESTIONS (LEVEL - 1) |40 Videos
  • SPEED, TIME AND DISTANCE

    ADDA247|Exercise Previous Year Questions|31 Videos
ADDA247-TIME AND WORK & PIPE AND CISTERN -PRELIMS QUESTIONS (LEVEL - 2)
  1. P alone and Q alone can do a piece of work in x and (3x)/(2) days resp...

    Text Solution

    |

  2. Anurag is 40% more efficient than Ayush. Ayush, Anurag and Shivam work...

    Text Solution

    |

  3. Neha who is 50% more efficient than Ritu who take double time than Pri...

    Text Solution

    |

  4. A, B and C can do a piece of work in 20 days, 10 days and 15 days resp...

    Text Solution

    |

  5. Working efficiency of 'A' is twice than that of 'B'.'A' and 'B' togeth...

    Text Solution

    |

  6. 7 men and 6 women together can complete a piece of work in 8 days and ...

    Text Solution

    |

  7. Deepak is 30% less efficient than Dharam and Dharam take 9 days less t...

    Text Solution

    |

  8. B is 40% less efficient than A and efficiency of C is (1)/(4)th the ef...

    Text Solution

    |

  9. If pipe A alone and Pipe B alone can fill a tank in 20 min and 30 min ...

    Text Solution

    |

  10. Pipe A, B and C can fill a cistern in 15 minutes, 24 minutes and 36 mi...

    Text Solution

    |

  11. A pipe can fill a cistern in 15 min and another pipe can fill the same...

    Text Solution

    |

  12. Two pipes A and B can fill a cistern in 12 hours and 8 hours respectiv...

    Text Solution

    |

  13. A and B working together can do a piece of work in 24 days, B and C wo...

    Text Solution

    |

  14. Three persons A, B and C together undertake to complete a piece of wor...

    Text Solution

    |

  15. A does 66(2)/(3)% of work in 8 days and is replaced by B and B complet...

    Text Solution

    |

  16. A and B working together can do a piece of work in 24 days, B and C wo...

    Text Solution

    |

  17. Three persons A, B and C together undertake to complete a piece of wor...

    Text Solution

    |

  18. A does 66(2)/(3)% of work in 8 days and is replaced by B and B complet...

    Text Solution

    |

  19. If (3p + 6) men can complete a work in 33(1)/(3)% less time than ((2)/...

    Text Solution

    |

  20. The efficiency of A is 40% more than that of B and efficiency of C is ...

    Text Solution

    |