Home
Class 14
MATHS
Veer is 40% less efficient than Bhavya a...

Veer is 40% less efficient than Bhavya and both complete the work together in 30 days, if Abhishek takes 10 days less as Veer and Bhavya takes together. Then find how many days will be required to complete the work, if all three work together?

A

16 days

B

12 days

C

10 days

D

8 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's break it down: ### Step 1: Determine the efficiencies of Veer and Bhavya. Let Bhavya's efficiency be 100 units of work per day. Since Veer is 40% less efficient than Bhavya, we can calculate Veer's efficiency as follows: \[ \text{Veer's efficiency} = 100 - (40\% \text{ of } 100) = 100 - 40 = 60 \text{ units of work per day.} \] ### Step 2: Calculate the combined efficiency of Veer and Bhavya. The combined efficiency of Veer and Bhavya is: \[ \text{Combined efficiency} = \text{Bhavya's efficiency} + \text{Veer's efficiency} = 100 + 60 = 160 \text{ units of work per day.} \] ### Step 3: Calculate the total work done. Since Veer and Bhavya together complete the work in 30 days, we can calculate the total work as follows: \[ \text{Total Work} = \text{Combined efficiency} \times \text{Time} = 160 \text{ units/day} \times 30 \text{ days} = 4800 \text{ units.} \] ### Step 4: Determine the time taken by Abhishek. We know that Abhishek takes 10 days less than the time taken by Veer and Bhavya together. The time taken by Veer and Bhavya together is 30 days, so: \[ \text{Time taken by Abhishek} = 30 - 10 = 20 \text{ days.} \] ### Step 5: Calculate Abhishek's efficiency. Using the total work calculated earlier, we can find Abhishek's efficiency: \[ \text{Abhishek's efficiency} = \frac{\text{Total Work}}{\text{Time taken by Abhishek}} = \frac{4800 \text{ units}}{20 \text{ days}} = 240 \text{ units of work per day.} \] ### Step 6: Calculate the total efficiency of all three working together. Now, we can find the total efficiency when all three work together: \[ \text{Total efficiency} = \text{Bhavya's efficiency} + \text{Veer's efficiency} + \text{Abhishek's efficiency} = 100 + 60 + 240 = 400 \text{ units of work per day.} \] ### Step 7: Calculate the time required for all three to complete the work together. Finally, we can find out how many days it will take for all three to complete the total work together: \[ \text{Time required} = \frac{\text{Total Work}}{\text{Total efficiency}} = \frac{4800 \text{ units}}{400 \text{ units/day}} = 12 \text{ days.} \] ### Final Answer: Thus, the time required for all three to complete the work together is **12 days**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PREVIOUS YEAR QUESTIONS |32 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PRELIMS QUESTIONS (LEVEL - 2) |40 Videos
  • SPEED, TIME AND DISTANCE

    ADDA247|Exercise Previous Year Questions|31 Videos
ADDA247-TIME AND WORK & PIPE AND CISTERN -MAINS QUESTIONS
  1. Abhishek can do a work in x hours. Bhavya who is 60% more efficient th...

    Text Solution

    |

  2. 20 men can complete a work in 12 days and 5 women are as efficient as ...

    Text Solution

    |

  3. Veer is 40% less efficient than Bhavya and both complete the work toge...

    Text Solution

    |

  4. A and B together can do a piece of work in 48 days and B & C together ...

    Text Solution

    |

  5. Ram can do a piece of work in 60 days and Shyam is 25% more efficient ...

    Text Solution

    |

  6. A can type 40 pages in 8 hours and B type 2 times more than that of A ...

    Text Solution

    |

  7. A certain work was started by 4 men and 10 women who completed 50% of ...

    Text Solution

    |

  8. A takes half as long to do a piece of work as B takes and C does it in...

    Text Solution

    |

  9. Each of A, B, C and D need a unique time to do a certain work. A can d...

    Text Solution

    |

  10. Each of A, B, C and D need a unique time to do a certain work. A can d...

    Text Solution

    |

  11. Working alone, A can complete a task in 'a' days and B in 'b' days. Th...

    Text Solution

    |

  12. 10 men and 12 women can complete a work in 5 days and 2 women and 6 ch...

    Text Solution

    |

  13. 10 men and 12 women can complete a work in 5 days and 2 women and 6 ch...

    Text Solution

    |

  14. A and B together can do a piece of work in 16 days. B and C together c...

    Text Solution

    |

  15. A and B together can do a piece of work in 16 days. B and C together c...

    Text Solution

    |

  16. 6 men complete a piece of work in 12 days. 8 women can complete the sa...

    Text Solution

    |

  17. 6 men complete a piece of work in 12 days. 8 women can complete the sa...

    Text Solution

    |

  18. Each of A, B, C and D require a unique time to do a certain work. B re...

    Text Solution

    |

  19. Each of A, B, C and D require a unique time to do a certain work. B re...

    Text Solution

    |

  20. A contractor took a construction work for Rs.400000 and employed 50 me...

    Text Solution

    |