Home
Class 14
MATHS
Each of A, B, C and D need a unique time...

Each of A, B, C and D need a unique time to do a certain work. A can do the work in x days and B can do the work in 2x days. A started the work and do it for `22(2)/(9)`days then he is replaced by B, who completed remaining work in same time as C and D together can complete the whole work. The ratio of the efficiency of C and D is 4 : 5. If C and D work for alternative days starting from C then they can do the total work in `44(1)/(2)`days.
A and B together can compete 225% of the work in how many days?

A

`66(2)/(3)` days

B

60 days

C

50 days

D

25 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will follow the information given in the question and derive the necessary values. ### Step 1: Determine the total work done by C and D - The efficiency ratio of C and D is given as 4:5. - When C and D work alternately starting from C, they complete the work in \(44 \frac{1}{2}\) days. - First, convert \(44 \frac{1}{2}\) days into improper fraction: \[ 44 \frac{1}{2} = \frac{89}{2} \text{ days} \] - In 2 days, C and D together complete: \[ 4 + 5 = 9 \text{ units of work} \] - In \(44\) days, they will complete: \[ \frac{89}{2} \div 2 = 44.5 \text{ days} \Rightarrow 44 \text{ complete cycles of 2 days} + 1 \text{ day of C} \] - Therefore, the total work done in 44 complete cycles: \[ 44 \times 9 = 396 \text{ units} \] - On the last day, C works for half a day, completing: \[ \frac{4}{2} = 2 \text{ units} \] - Thus, the total work done is: \[ 396 + 2 = 398 \text{ units} \] ### Step 2: Calculate the efficiencies of A and B - Let A's time to complete the work be \(x\) days, then B's time is \(2x\) days. - The efficiency of A is: \[ \text{Efficiency of A} = \frac{1}{x} \text{ (work per day)} \] - The efficiency of B is: \[ \text{Efficiency of B} = \frac{1}{2x} \] ### Step 3: Calculate the work done by A in \(22 \frac{2}{9}\) days - Convert \(22 \frac{2}{9}\) into improper fraction: \[ 22 \frac{2}{9} = \frac{200}{9} \text{ days} \] - Work done by A in this time: \[ \text{Work by A} = \frac{200}{9} \times \frac{1}{x} = \frac{200}{9x} \] ### Step 4: Calculate remaining work - Total work is \(398\) units, so remaining work after A's contribution is: \[ \text{Remaining Work} = 398 - \frac{200}{9x} \] ### Step 5: Determine the time taken by B to finish the remaining work - Since B completes the remaining work in the same time as C and D can complete the whole work, we know: \[ \frac{398 - \frac{200}{9x}}{\frac{1}{2x}} = \text{Time taken by B} \] - The time taken by C and D together to complete the whole work is: \[ \frac{398}{\frac{9}{2}} = \frac{398 \times 2}{9} = \frac{796}{9} \text{ days} \] ### Step 6: Set up the equation - Equating the time taken by B to finish the remaining work to the time taken by C and D: \[ \frac{398 - \frac{200}{9x}}{\frac{1}{2x}} = \frac{796}{9} \] - Solving this equation will yield the value of \(x\). ### Step 7: Calculate the total work A and B can complete together in 225% - Total work is \(398\) units, so \(225\%\) of the work is: \[ 398 \times \frac{225}{100} = 448.5 \text{ units} \] - Combined efficiency of A and B: \[ \text{Combined Efficiency} = \frac{1}{x} + \frac{1}{2x} = \frac{3}{2x} \] - Time taken by A and B together to complete \(448.5\) units: \[ \text{Time} = \frac{448.5}{\frac{3}{2x}} = \frac{448.5 \times 2x}{3} = \frac{897x}{3} \] ### Step 8: Substitute \(x\) and calculate the final answer - Substitute the value of \(x\) obtained from previous calculations to find the total time.
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PREVIOUS YEAR QUESTIONS |32 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PRELIMS QUESTIONS (LEVEL - 2) |40 Videos
  • SPEED, TIME AND DISTANCE

    ADDA247|Exercise Previous Year Questions|31 Videos
ADDA247-TIME AND WORK & PIPE AND CISTERN -MAINS QUESTIONS
  1. A takes half as long to do a piece of work as B takes and C does it in...

    Text Solution

    |

  2. Each of A, B, C and D need a unique time to do a certain work. A can d...

    Text Solution

    |

  3. Each of A, B, C and D need a unique time to do a certain work. A can d...

    Text Solution

    |

  4. Working alone, A can complete a task in 'a' days and B in 'b' days. Th...

    Text Solution

    |

  5. 10 men and 12 women can complete a work in 5 days and 2 women and 6 ch...

    Text Solution

    |

  6. 10 men and 12 women can complete a work in 5 days and 2 women and 6 ch...

    Text Solution

    |

  7. A and B together can do a piece of work in 16 days. B and C together c...

    Text Solution

    |

  8. A and B together can do a piece of work in 16 days. B and C together c...

    Text Solution

    |

  9. 6 men complete a piece of work in 12 days. 8 women can complete the sa...

    Text Solution

    |

  10. 6 men complete a piece of work in 12 days. 8 women can complete the sa...

    Text Solution

    |

  11. Each of A, B, C and D require a unique time to do a certain work. B re...

    Text Solution

    |

  12. Each of A, B, C and D require a unique time to do a certain work. B re...

    Text Solution

    |

  13. A contractor took a construction work for Rs.400000 and employed 50 me...

    Text Solution

    |

  14. A is thrice as good a workman as B and therefore is able to finish a j...

    Text Solution

    |

  15. A is thrice as good a workman as B and therefore is able to finish a j...

    Text Solution

    |

  16. Working efficiency of A is 20% more than that of B, who can complete a...

    Text Solution

    |

  17. Working efficiency of A is 20% more than that of B, who can complete a...

    Text Solution

    |

  18. Working efficiency of A is 20% more than that of B, who can complete a...

    Text Solution

    |

  19. A and B can do a work in 30 days, B and C do same work in 24 days. If ...

    Text Solution

    |

  20. P, Q and R are 3 small pumps fitted to a tank. S is a large pump fitte...

    Text Solution

    |