Home
Class 14
MATHS
Working alone, A can complete a task in ...

Working alone, A can complete a task in 'a' days and B in 'b' days. They take turns in doing the task with each working 2 days at a time. If A starts they finish the task in exactly 10 days. If B starts, they take half a day more. How long does it take to complete the task if they both work together?

A

`5(1)/(3)`days

B

`5(1)/(7)`days

C

`5(5)/(9)`days

D

`5(5)/(11)`days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first analyze the information given and then derive the necessary equations to find the solution. ### Step 1: Understand the Work Done by A and B - Let the total work be denoted as W. - A can complete the work in 'a' days, so A's work rate is \( \frac{W}{a} \) per day. - B can complete the work in 'b' days, so B's work rate is \( \frac{W}{b} \) per day. ### Step 2: Work Done in 10 Days When A Starts - A works for the first 2 days, then B works for the next 2 days, and this pattern continues. - In 10 days, A works for 6 days (2 days at a time for 5 cycles) and B works for 4 days (2 days at a time for 4 cycles). The work done by A in 6 days: \[ \text{Work by A} = 6 \times \frac{W}{a} = \frac{6W}{a} \] The work done by B in 4 days: \[ \text{Work by B} = 4 \times \frac{W}{b} = \frac{4W}{b} \] Since they complete the work in 10 days: \[ \frac{6W}{a} + \frac{4W}{b} = W \] Dividing the entire equation by W: \[ \frac{6}{a} + \frac{4}{b} = 1 \quad \text{(Equation 1)} \] ### Step 3: Work Done in 10.5 Days When B Starts - If B starts, they work for 10.5 days. B works for 6 days (2 days at a time for 5 cycles) and A works for 4.5 days (2 days at a time for 4 cycles and then half a day). The work done by B in 6 days: \[ \text{Work by B} = 6 \times \frac{W}{b} = \frac{6W}{b} \] The work done by A in 4.5 days: \[ \text{Work by A} = 4.5 \times \frac{W}{a} = \frac{4.5W}{a} \] Since they complete the work in 10.5 days: \[ \frac{6W}{b} + \frac{4.5W}{a} = W \] Dividing the entire equation by W: \[ \frac{6}{b} + \frac{4.5}{a} = 1 \quad \text{(Equation 2)} \] ### Step 4: Solve the Equations Now we have two equations: 1. \( \frac{6}{a} + \frac{4}{b} = 1 \) 2. \( \frac{6}{b} + \frac{4.5}{a} = 1 \) From Equation 1, we can express \( \frac{4}{b} \): \[ \frac{4}{b} = 1 - \frac{6}{a} \implies b = \frac{4a}{a - 6} \] Substituting \( b \) in Equation 2: \[ \frac{6(a - 6)}{4a} + \frac{4.5}{a} = 1 \] Clearing the fractions and solving will yield the values of a and b. ### Step 5: Calculate the Time Taken When A and B Work Together When A and B work together, their combined work rate is: \[ \text{Combined Rate} = \frac{W}{a} + \frac{W}{b} = W \left( \frac{1}{a} + \frac{1}{b} \right) \] The time taken to complete the work together is: \[ T = \frac{W}{\left( \frac{W}{a} + \frac{W}{b} \right)} = \frac{1}{\left( \frac{1}{a} + \frac{1}{b} \right)} \] Substituting the values of a and b will give the final answer.
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PREVIOUS YEAR QUESTIONS |32 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PRELIMS QUESTIONS (LEVEL - 2) |40 Videos
  • SPEED, TIME AND DISTANCE

    ADDA247|Exercise Previous Year Questions|31 Videos
ADDA247-TIME AND WORK & PIPE AND CISTERN -MAINS QUESTIONS
  1. Each of A, B, C and D need a unique time to do a certain work. A can d...

    Text Solution

    |

  2. Each of A, B, C and D need a unique time to do a certain work. A can d...

    Text Solution

    |

  3. Working alone, A can complete a task in 'a' days and B in 'b' days. Th...

    Text Solution

    |

  4. 10 men and 12 women can complete a work in 5 days and 2 women and 6 ch...

    Text Solution

    |

  5. 10 men and 12 women can complete a work in 5 days and 2 women and 6 ch...

    Text Solution

    |

  6. A and B together can do a piece of work in 16 days. B and C together c...

    Text Solution

    |

  7. A and B together can do a piece of work in 16 days. B and C together c...

    Text Solution

    |

  8. 6 men complete a piece of work in 12 days. 8 women can complete the sa...

    Text Solution

    |

  9. 6 men complete a piece of work in 12 days. 8 women can complete the sa...

    Text Solution

    |

  10. Each of A, B, C and D require a unique time to do a certain work. B re...

    Text Solution

    |

  11. Each of A, B, C and D require a unique time to do a certain work. B re...

    Text Solution

    |

  12. A contractor took a construction work for Rs.400000 and employed 50 me...

    Text Solution

    |

  13. A is thrice as good a workman as B and therefore is able to finish a j...

    Text Solution

    |

  14. A is thrice as good a workman as B and therefore is able to finish a j...

    Text Solution

    |

  15. Working efficiency of A is 20% more than that of B, who can complete a...

    Text Solution

    |

  16. Working efficiency of A is 20% more than that of B, who can complete a...

    Text Solution

    |

  17. Working efficiency of A is 20% more than that of B, who can complete a...

    Text Solution

    |

  18. A and B can do a work in 30 days, B and C do same work in 24 days. If ...

    Text Solution

    |

  19. P, Q and R are 3 small pumps fitted to a tank. S is a large pump fitte...

    Text Solution

    |

  20. P, Q and R are 3 small pumps fitted to a tank. S is a large pump fitte...

    Text Solution

    |