Home
Class 14
MATHS
A and B together can do a piece of work ...

A and B together can do a piece of work in 16 days. B and C together can do the same work in 32 days. C can complete the same work in 80 days. After A has worked for 4 days, B for 12 days, time taken by C to complete the remaining job is x days.
P, Q and R take (x - 28) days, (x - 18) days and (x - 8) days respectively to complete an another job. The three work in a rotation to complete the job with only 1 person working on a day. Who should start the job so that the job is completed in the least possible time?

A

P

B

Q

C

R

D

Any one of the three

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step-by-step, we will break it down into manageable parts. ### Step 1: Determine the efficiencies of A, B, and C 1. **A and B together can do the work in 16 days.** - Efficiency of A + B = Total Work / Time = 160 / 16 = 10 2. **B and C together can do the work in 32 days.** - Efficiency of B + C = Total Work / Time = 160 / 32 = 5 3. **C can complete the work in 80 days.** - Efficiency of C = Total Work / Time = 160 / 80 = 2 Now we have: - Efficiency of A + B = 10 - Efficiency of B + C = 5 - Efficiency of C = 2 ### Step 2: Find the efficiency of A and B separately Using the equations: - From A + B = 10 and C = 2, we can find B: - B + C = 5 - B + 2 = 5 → B = 3 Now substituting B into A + B: - A + 3 = 10 → A = 7 So, we have: - Efficiency of A = 7 - Efficiency of B = 3 - Efficiency of C = 2 ### Step 3: Calculate the work done by A, B, and C 1. **A works for 4 days:** - Work done by A = Efficiency of A × Days worked = 7 × 4 = 28 2. **B works for 12 days:** - Work done by B = Efficiency of B × Days worked = 3 × 12 = 36 3. **Total work done by A and B:** - Total work done = 28 + 36 = 64 4. **Remaining work:** - Remaining work = Total Work - Work done = 160 - 64 = 96 ### Step 4: Calculate time taken by C to complete the remaining work 1. **C's efficiency is 2:** - Time taken by C = Remaining Work / Efficiency of C = 96 / 2 = 48 days Thus, \( x = 48 \). ### Step 5: Determine the time taken by P, Q, and R 1. **P takes (x - 28) days:** - P = 48 - 28 = 20 days 2. **Q takes (x - 18) days:** - Q = 48 - 18 = 30 days 3. **R takes (x - 8) days:** - R = 48 - 8 = 40 days ### Step 6: Calculate efficiencies of P, Q, and R 1. **Efficiency of P:** - Efficiency of P = Total Work / Time = 160 / 20 = 8 2. **Efficiency of Q:** - Efficiency of Q = Total Work / Time = 160 / 30 = 5.33 3. **Efficiency of R:** - Efficiency of R = Total Work / Time = 160 / 40 = 4 ### Step 7: Determine the optimal starting person 1. **Total work done in one cycle (3 days):** - Work done in 3 days = Efficiency of P + Efficiency of Q + Efficiency of R = 8 + 5.33 + 4 = 17.33 2. **Total cycles needed:** - Total work = 160 - Cycles = Total work / Work done in 3 days = 160 / 17.33 ≈ 9.23 cycles 3. **Remaining work after 9 cycles:** - Work done in 9 cycles = 9 × 17.33 = 156 - Remaining work = 160 - 156 = 4 4. **Determine who should do the remaining work:** - If P starts, he can do 8 work in a day. - If Q starts, he can do 5.33 work in a day. - If R starts, he can do 4 work in a day. Since P has the highest efficiency, he should start the job to complete it in the least possible time. ### Final Answer: **P should start the job.** ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PREVIOUS YEAR QUESTIONS |32 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PRELIMS QUESTIONS (LEVEL - 2) |40 Videos
  • SPEED, TIME AND DISTANCE

    ADDA247|Exercise Previous Year Questions|31 Videos
ADDA247-TIME AND WORK & PIPE AND CISTERN -MAINS QUESTIONS
  1. 10 men and 12 women can complete a work in 5 days and 2 women and 6 ch...

    Text Solution

    |

  2. 10 men and 12 women can complete a work in 5 days and 2 women and 6 ch...

    Text Solution

    |

  3. A and B together can do a piece of work in 16 days. B and C together c...

    Text Solution

    |

  4. A and B together can do a piece of work in 16 days. B and C together c...

    Text Solution

    |

  5. 6 men complete a piece of work in 12 days. 8 women can complete the sa...

    Text Solution

    |

  6. 6 men complete a piece of work in 12 days. 8 women can complete the sa...

    Text Solution

    |

  7. Each of A, B, C and D require a unique time to do a certain work. B re...

    Text Solution

    |

  8. Each of A, B, C and D require a unique time to do a certain work. B re...

    Text Solution

    |

  9. A contractor took a construction work for Rs.400000 and employed 50 me...

    Text Solution

    |

  10. A is thrice as good a workman as B and therefore is able to finish a j...

    Text Solution

    |

  11. A is thrice as good a workman as B and therefore is able to finish a j...

    Text Solution

    |

  12. Working efficiency of A is 20% more than that of B, who can complete a...

    Text Solution

    |

  13. Working efficiency of A is 20% more than that of B, who can complete a...

    Text Solution

    |

  14. Working efficiency of A is 20% more than that of B, who can complete a...

    Text Solution

    |

  15. A and B can do a work in 30 days, B and C do same work in 24 days. If ...

    Text Solution

    |

  16. P, Q and R are 3 small pumps fitted to a tank. S is a large pump fitte...

    Text Solution

    |

  17. P, Q and R are 3 small pumps fitted to a tank. S is a large pump fitte...

    Text Solution

    |

  18. Bibhor takes 3 hours to fetch as much water as Ahmed can fetch in 2 ho...

    Text Solution

    |

  19. Bibhor takes 3 hours to fetch as much water as Ahmed can fetch in 2 ho...

    Text Solution

    |

  20. The daily work of two men is equal to that of 3 women or that of 4 you...

    Text Solution

    |