Home
Class 14
MATHS
Each of A, B, C and D require a unique t...

Each of A, B, C and D require a unique time to do a certain work. B requires twice the time A requires to do the work. A started the work and do it for 10 days, then he is replaced by B, who worked for four more days than A worked, after that B also left the work. C and D started working on alternative days starting from C and both completed the remaining work in 30 days. The ratio of the efficiency of C and D is 5 : 3 and both together did 32% of the total work.
In how many days, A alone can complete twice the work?

A

25 days

B

30 days

C

40 days

D

50 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will analyze the work done by A, B, C, and D, and then calculate how many days A alone can complete twice the work. ### Step 1: Understand the efficiencies of A, B, C, and D Let the time taken by A to complete the work be \( x \) days. Then, the time taken by B will be \( 2x \) days (since B requires twice the time A requires). The efficiencies can be calculated as follows: - Efficiency of A = \( \frac{1}{x} \) - Efficiency of B = \( \frac{1}{2x} \) ### Step 2: Calculate the work done by A and B A works for 10 days: - Work done by A in 10 days = \( 10 \times \frac{1}{x} = \frac{10}{x} \) B works for 4 more days than A worked. Since A worked for 10 days, B works for \( 10 + 4 = 14 \) days: - Work done by B in 14 days = \( 14 \times \frac{1}{2x} = \frac{14}{2x} = \frac{7}{x} \) ### Step 3: Total work done by A and B Total work done by A and B together: \[ \text{Total work done} = \frac{10}{x} + \frac{7}{x} = \frac{17}{x} \] ### Step 4: Remaining work and work done by C and D Let the total work be \( W \). The remaining work after A and B is: \[ W - \frac{17}{x} \] C and D work on alternate days starting with C and complete the remaining work in 30 days. The ratio of their efficiencies is 5:3. Let the efficiency of C be \( 5k \) and the efficiency of D be \( 3k \). In 2 days, they complete: \[ 5k + 3k = 8k \] In 30 days, they complete: \[ \frac{30}{2} \times 8k = 15 \times 8k = 120k \] ### Step 5: Relate the work done by C and D to the total work According to the problem, the work done by C and D together is 32% of the total work: \[ 120k = 0.32W \] ### Step 6: Calculate the total work \( W \) From the above equation, we can express \( W \): \[ W = \frac{120k}{0.32} = 375k \] ### Step 7: Calculate the total work done by A and B We know: \[ W = \frac{17}{x} + \text{Remaining work} \] The remaining work is: \[ W - \frac{17}{x} = 375k - \frac{17}{x} \] ### Step 8: Calculate the efficiency of A We have: \[ \frac{17}{x} + 120k = 375k \] This gives us: \[ \frac{17}{x} = 375k - 120k = 255k \] Thus: \[ x = \frac{17}{255k} = \frac{17}{255} \cdot \frac{1}{k} \] ### Step 9: Calculate the time taken by A to complete twice the work The efficiency of A is \( \frac{1}{x} \), so the time taken by A to complete twice the work \( 2W \) is: \[ \text{Time} = \frac{2W}{\text{Efficiency of A}} = \frac{2 \times 375k}{\frac{1}{x}} = 2 \times 375k \times x \] Substituting \( x \): \[ = 2 \times 375k \times \frac{17}{255} \cdot \frac{1}{k} = 2 \times 375 \times \frac{17}{255} \] Calculating this gives: \[ = \frac{2 \times 375 \times 17}{255} = \frac{12750}{255} = 50 \] ### Final Answer A alone can complete twice the work in **50 days**.
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PREVIOUS YEAR QUESTIONS |32 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PRELIMS QUESTIONS (LEVEL - 2) |40 Videos
  • SPEED, TIME AND DISTANCE

    ADDA247|Exercise Previous Year Questions|31 Videos
ADDA247-TIME AND WORK & PIPE AND CISTERN -MAINS QUESTIONS
  1. 6 men complete a piece of work in 12 days. 8 women can complete the sa...

    Text Solution

    |

  2. 6 men complete a piece of work in 12 days. 8 women can complete the sa...

    Text Solution

    |

  3. Each of A, B, C and D require a unique time to do a certain work. B re...

    Text Solution

    |

  4. Each of A, B, C and D require a unique time to do a certain work. B re...

    Text Solution

    |

  5. A contractor took a construction work for Rs.400000 and employed 50 me...

    Text Solution

    |

  6. A is thrice as good a workman as B and therefore is able to finish a j...

    Text Solution

    |

  7. A is thrice as good a workman as B and therefore is able to finish a j...

    Text Solution

    |

  8. Working efficiency of A is 20% more than that of B, who can complete a...

    Text Solution

    |

  9. Working efficiency of A is 20% more than that of B, who can complete a...

    Text Solution

    |

  10. Working efficiency of A is 20% more than that of B, who can complete a...

    Text Solution

    |

  11. A and B can do a work in 30 days, B and C do same work in 24 days. If ...

    Text Solution

    |

  12. P, Q and R are 3 small pumps fitted to a tank. S is a large pump fitte...

    Text Solution

    |

  13. P, Q and R are 3 small pumps fitted to a tank. S is a large pump fitte...

    Text Solution

    |

  14. Bibhor takes 3 hours to fetch as much water as Ahmed can fetch in 2 ho...

    Text Solution

    |

  15. Bibhor takes 3 hours to fetch as much water as Ahmed can fetch in 2 ho...

    Text Solution

    |

  16. The daily work of two men is equal to that of 3 women or that of 4 you...

    Text Solution

    |

  17. The daily work of two men is equal to that of 3 women or that of 4 you...

    Text Solution

    |

  18. A can complete a work in 20 days and B can complete the same work in 1...

    Text Solution

    |

  19. Time taken by A and B to complete a work is in the ratio 4 : 5. A alon...

    Text Solution

    |

  20. There are three pipes connected to the tank. Pipe A and pipe B can fil...

    Text Solution

    |