Home
Class 14
MATHS
A is thrice as good a workman as B and t...

A is thrice as good a workman as B and therefore is able to finish a job in 80 days less than B. If A and B complete `(5)/(8)`th of the job and then A is replaced by C, the remaining job is done by B and C in 15 days. If A and B complete `(5)/(12)`th of the job and then B is replaced by D the remaining job is done by A and D in 10 days.
How long will it take to complete the job, if A,B,C and D working together?

A

12 days

B

10 days

C

15 days

D

18 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first determine the efficiencies of A, B, C, and D, and then calculate how long it will take for all of them to complete the job together. ### Step 1: Determine the efficiencies of A and B Given that A is thrice as good a workman as B, we can denote: - Efficiency of B = 1 unit of work per day - Efficiency of A = 3 units of work per day Let the time taken by B to complete the job be \( x \) days. Since A finishes the job in 80 days less than B, we have: \[ \text{Time taken by A} = x - 80 \] Using the formula for work: \[ \text{Total Work} = \text{Efficiency} \times \text{Time} \] For A: \[ 3(x - 80) = \text{Total Work} \] For B: \[ 1 \times x = \text{Total Work} \] Setting these equal gives: \[ 3(x - 80) = x \] Expanding and simplifying: \[ 3x - 240 = x \] \[ 2x = 240 \] \[ x = 120 \] So, B takes 120 days to complete the job, and A takes: \[ 120 - 80 = 40 \text{ days} \] ### Step 2: Calculate the total work Using B's time: \[ \text{Total Work} = 1 \times 120 = 120 \text{ units} \] ### Step 3: Work done by A and B together A and B together complete \( \frac{5}{8} \) of the job: \[ \text{Work done} = \frac{5}{8} \times 120 = 75 \text{ units} \] ### Step 4: Remaining work Remaining work after A and B: \[ 120 - 75 = 45 \text{ units} \] ### Step 5: Work done by B and C B and C complete the remaining 45 units in 15 days. Therefore, their combined efficiency is: \[ \text{Efficiency of B and C} = \frac{45}{15} = 3 \text{ units per day} \] Since B's efficiency is 1 unit per day, we can find C's efficiency: \[ 1 + C = 3 \] \[ C = 2 \text{ units per day} \] ### Step 6: Work done by A and B together again Next, A and B complete \( \frac{5}{12} \) of the job: \[ \text{Work done} = \frac{5}{12} \times 120 = 50 \text{ units} \] ### Step 7: Remaining work Remaining work after A and B: \[ 120 - 50 = 70 \text{ units} \] ### Step 8: Work done by A and D A and D complete the remaining 70 units in 10 days. Therefore, their combined efficiency is: \[ \text{Efficiency of A and D} = \frac{70}{10} = 7 \text{ units per day} \] Since A's efficiency is 3 units per day, we can find D's efficiency: \[ 3 + D = 7 \] \[ D = 4 \text{ units per day} \] ### Step 9: Total efficiency of A, B, C, and D together Now, we can find the total efficiency when A, B, C, and D work together: \[ \text{Total Efficiency} = A + B + C + D = 3 + 1 + 2 + 4 = 10 \text{ units per day} \] ### Step 10: Time taken to complete the job together Finally, to find the time taken to complete the entire job when A, B, C, and D work together: \[ \text{Time} = \frac{\text{Total Work}}{\text{Total Efficiency}} = \frac{120}{10} = 12 \text{ days} \] ### Final Answer Thus, it will take **12 days** to complete the job if A, B, C, and D work together. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PREVIOUS YEAR QUESTIONS |32 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PRELIMS QUESTIONS (LEVEL - 2) |40 Videos
  • SPEED, TIME AND DISTANCE

    ADDA247|Exercise Previous Year Questions|31 Videos
ADDA247-TIME AND WORK & PIPE AND CISTERN -MAINS QUESTIONS
  1. Each of A, B, C and D require a unique time to do a certain work. B re...

    Text Solution

    |

  2. A contractor took a construction work for Rs.400000 and employed 50 me...

    Text Solution

    |

  3. A is thrice as good a workman as B and therefore is able to finish a j...

    Text Solution

    |

  4. A is thrice as good a workman as B and therefore is able to finish a j...

    Text Solution

    |

  5. Working efficiency of A is 20% more than that of B, who can complete a...

    Text Solution

    |

  6. Working efficiency of A is 20% more than that of B, who can complete a...

    Text Solution

    |

  7. Working efficiency of A is 20% more than that of B, who can complete a...

    Text Solution

    |

  8. A and B can do a work in 30 days, B and C do same work in 24 days. If ...

    Text Solution

    |

  9. P, Q and R are 3 small pumps fitted to a tank. S is a large pump fitte...

    Text Solution

    |

  10. P, Q and R are 3 small pumps fitted to a tank. S is a large pump fitte...

    Text Solution

    |

  11. Bibhor takes 3 hours to fetch as much water as Ahmed can fetch in 2 ho...

    Text Solution

    |

  12. Bibhor takes 3 hours to fetch as much water as Ahmed can fetch in 2 ho...

    Text Solution

    |

  13. The daily work of two men is equal to that of 3 women or that of 4 you...

    Text Solution

    |

  14. The daily work of two men is equal to that of 3 women or that of 4 you...

    Text Solution

    |

  15. A can complete a work in 20 days and B can complete the same work in 1...

    Text Solution

    |

  16. Time taken by A and B to complete a work is in the ratio 4 : 5. A alon...

    Text Solution

    |

  17. There are three pipes connected to the tank. Pipe A and pipe B can fil...

    Text Solution

    |

  18. Q is 50% more efficient than P, who completed a task in 45 days and R ...

    Text Solution

    |

  19. There are 2 inlet pipes and 1 outlet pipe assigned to fill a tank. If ...

    Text Solution

    |

  20. A ship is 108 km away from the shore when a leak appears on its bottom...

    Text Solution

    |