Home
Class 14
MATHS
A is thrice as good a workman as B and t...

A is thrice as good a workman as B and therefore is able to finish a job in 80 days less than B. If A and B complete `(5)/(8)`th of the job and then A is replaced by C, the remaining job is done by B and C in 15 days. If A and B complete `(5)/(12)`th of the job and then B is replaced by D the remaining job is done by A and D in 10 days.
The job is completed in the following manner: A and B work on day 1, B and C work on day 2, C and D work on day 3, D and A work on day 4 and so on. How long will it take for the job to be completed in this manner?

A

30 days

B

24 days

C

18 days

D

15 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will analyze the information given about the work done by A, B, C, and D, and calculate the total time taken to complete the job. ### Step 1: Determine the efficiencies of A and B Given that A is thrice as good a workman as B, we can denote: - Efficiency of B = 1 unit of work per day - Efficiency of A = 3 units of work per day ### Step 2: Calculate the time taken by A and B Let the time taken by B to complete the job be \( x \) days. Therefore, the time taken by A is \( x - 80 \) days. Since A is thrice as efficient as B, we can set up the equation based on their efficiencies: \[ \text{Total work} = \text{Efficiency} \times \text{Time} \] For A: \[ \text{Total work} = 3 \times (x - 80) \] For B: \[ \text{Total work} = 1 \times x \] Equating the two expressions for total work: \[ 3(x - 80) = x \] \[ 3x - 240 = x \] \[ 2x = 240 \] \[ x = 120 \] So, B takes 120 days to complete the job, and A takes: \[ 120 - 80 = 40 \text{ days} \] ### Step 3: Calculate the total work Using B's time: \[ \text{Total work} = 1 \times 120 = 120 \text{ units} \] ### Step 4: Work done by A and B together A and B complete \( \frac{5}{8} \) of the job: \[ \text{Work done} = \frac{5}{8} \times 120 = 75 \text{ units} \] Remaining work: \[ 120 - 75 = 45 \text{ units} \] ### Step 5: Work done by B and C B and C complete the remaining work in 15 days: Let C's efficiency be \( c \). The total efficiency of B and C is: \[ 1 + c \] The work done in 15 days is: \[ 15(1 + c) = 45 \] \[ 1 + c = 3 \implies c = 2 \] ### Step 6: Work done by A and D Next, A and B complete \( \frac{5}{12} \) of the job: \[ \text{Work done} = \frac{5}{12} \times 120 = 50 \text{ units} \] Remaining work: \[ 120 - 50 = 70 \text{ units} \] A and D complete this remaining work in 10 days: Let D's efficiency be \( d \). The total efficiency of A and D is: \[ 3 + d \] The work done in 10 days is: \[ 10(3 + d) = 70 \] \[ 3 + d = 7 \implies d = 4 \] ### Step 7: Summary of efficiencies - Efficiency of A = 3 - Efficiency of B = 1 - Efficiency of C = 2 - Efficiency of D = 4 ### Step 8: Work done in a cycle of 4 days Now, we calculate the work done in the cycle of 4 days: 1. Day 1: A + B = 3 + 1 = 4 units 2. Day 2: B + C = 1 + 2 = 3 units 3. Day 3: C + D = 2 + 4 = 6 units 4. Day 4: D + A = 4 + 3 = 7 units Total work done in 4 days: \[ 4 + 3 + 6 + 7 = 20 \text{ units} \] ### Step 9: Total days to complete the job Total work = 120 units. The number of complete cycles needed: \[ \frac{120}{20} = 6 \text{ cycles} \] Each cycle takes 4 days: \[ 6 \times 4 = 24 \text{ days} \] Thus, the total time taken to complete the job is **24 days**.
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PREVIOUS YEAR QUESTIONS |32 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PRELIMS QUESTIONS (LEVEL - 2) |40 Videos
  • SPEED, TIME AND DISTANCE

    ADDA247|Exercise Previous Year Questions|31 Videos
ADDA247-TIME AND WORK & PIPE AND CISTERN -MAINS QUESTIONS
  1. A contractor took a construction work for Rs.400000 and employed 50 me...

    Text Solution

    |

  2. A is thrice as good a workman as B and therefore is able to finish a j...

    Text Solution

    |

  3. A is thrice as good a workman as B and therefore is able to finish a j...

    Text Solution

    |

  4. Working efficiency of A is 20% more than that of B, who can complete a...

    Text Solution

    |

  5. Working efficiency of A is 20% more than that of B, who can complete a...

    Text Solution

    |

  6. Working efficiency of A is 20% more than that of B, who can complete a...

    Text Solution

    |

  7. A and B can do a work in 30 days, B and C do same work in 24 days. If ...

    Text Solution

    |

  8. P, Q and R are 3 small pumps fitted to a tank. S is a large pump fitte...

    Text Solution

    |

  9. P, Q and R are 3 small pumps fitted to a tank. S is a large pump fitte...

    Text Solution

    |

  10. Bibhor takes 3 hours to fetch as much water as Ahmed can fetch in 2 ho...

    Text Solution

    |

  11. Bibhor takes 3 hours to fetch as much water as Ahmed can fetch in 2 ho...

    Text Solution

    |

  12. The daily work of two men is equal to that of 3 women or that of 4 you...

    Text Solution

    |

  13. The daily work of two men is equal to that of 3 women or that of 4 you...

    Text Solution

    |

  14. A can complete a work in 20 days and B can complete the same work in 1...

    Text Solution

    |

  15. Time taken by A and B to complete a work is in the ratio 4 : 5. A alon...

    Text Solution

    |

  16. There are three pipes connected to the tank. Pipe A and pipe B can fil...

    Text Solution

    |

  17. Q is 50% more efficient than P, who completed a task in 45 days and R ...

    Text Solution

    |

  18. There are 2 inlet pipes and 1 outlet pipe assigned to fill a tank. If ...

    Text Solution

    |

  19. A ship is 108 km away from the shore when a leak appears on its bottom...

    Text Solution

    |

  20. There are four pipes connected to a tank - A, B, C and D. A & D are in...

    Text Solution

    |