Home
Class 14
MATHS
Working efficiency of A is 20% more than...

Working efficiency of A is 20% more than that of B, who can complete a work 'X' in 36 days.
B and C together started to complete the work 'X' and after 10 days they both left the work and then remaining work is done by A alone in 15 days.
A and C together started to complete another work 'Y' and after working for 12 days they both left the work and Remaining work is done by B alone in 16 days. If D first completed work 'X' and then completed work 'Y' in total 38 days.
It is given that efficiency of all, in completing work 'X' and work 'Y' is same.
A, B and C working together completed `(1)/(3)`rd of work 'X', and then A and C are replaced by D. Now remaining of work 'X' is completed by B and D together. For how many days B worked?

A

12 days

B

10 days

C

15 days

D

4 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's break it down systematically. ### Step 1: Determine the efficiencies of A, B, C, and D - Let the efficiency of B be \( x \). - Since A's efficiency is 20% more than B's, we have: \[ A = x + 0.2x = 1.2x \] - Given that B can complete work X in 36 days, the total work \( W \) can be calculated as: \[ W = \text{Efficiency} \times \text{Time} = x \times 36 \] - Therefore, the total work \( W = 36x \). ### Step 2: Calculate the total work in terms of B's efficiency - From the information given, we can also express the total work as: \[ W = 180 \quad \text{(as derived from the video)} \] - Setting these equal gives: \[ 36x = 180 \implies x = 5 \] - Thus, the efficiencies are: \[ B = 5, \quad A = 1.2 \times 5 = 6, \quad \text{and we need to find C's efficiency.} \] ### Step 3: Find C's efficiency - From the work done by B and C together for 10 days: \[ \text{Work done by B and C in 10 days} = 10(B + C) = 10(5 + C) \] - The remaining work is completed by A in 15 days: \[ \text{Remaining work} = 15A = 15 \times 6 = 90 \] - Therefore, the total work can also be expressed as: \[ 10(5 + C) + 90 = 180 \] \[ 50 + 10C + 90 = 180 \implies 10C = 40 \implies C = 4 \] ### Step 4: Efficiency of D - A and C work together for 12 days, and then B completes the remaining work in 16 days. - The total work done by A and C in 12 days: \[ 12(A + C) = 12(6 + 4) = 120 \] - The remaining work done by B alone in 16 days: \[ 16B = 16 \times 5 = 80 \] - Therefore, the total work for Y is: \[ 120 + 80 = 200 \] ### Step 5: Calculate D's efficiency - D completes both works in 38 days: \[ \frac{180}{D} + \frac{200}{D} = 38 \implies \frac{380}{D} = 38 \implies D = 10 \] ### Step 6: Work done by A, B, and C together - A, B, and C together complete \( \frac{1}{3} \) of work X: \[ \text{Work done} = \frac{1}{3} \times 180 = 60 \] - Their combined efficiency: \[ A + B + C = 6 + 5 + 4 = 15 \] - Time taken to complete 60 work: \[ \text{Time} = \frac{60}{15} = 4 \text{ days} \] ### Step 7: Remaining work done by B and D - Remaining work after A, B, and C completed \( \frac{1}{3} \): \[ \text{Remaining work} = 180 - 60 = 120 \] - B and D together work on the remaining work: \[ \text{Efficiency of B and D} = 5 + 10 = 15 \] - Time taken to complete the remaining work: \[ \text{Time} = \frac{120}{15} = 8 \text{ days} \] ### Step 8: Total days worked by B - B worked for: \[ 4 \text{ days (with A and C)} + 8 \text{ days (with D)} = 12 \text{ days} \] ### Final Answer B worked for **12 days**.
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PREVIOUS YEAR QUESTIONS |32 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PRELIMS QUESTIONS (LEVEL - 2) |40 Videos
  • SPEED, TIME AND DISTANCE

    ADDA247|Exercise Previous Year Questions|31 Videos
ADDA247-TIME AND WORK & PIPE AND CISTERN -MAINS QUESTIONS
  1. A is thrice as good a workman as B and therefore is able to finish a j...

    Text Solution

    |

  2. A is thrice as good a workman as B and therefore is able to finish a j...

    Text Solution

    |

  3. Working efficiency of A is 20% more than that of B, who can complete a...

    Text Solution

    |

  4. Working efficiency of A is 20% more than that of B, who can complete a...

    Text Solution

    |

  5. Working efficiency of A is 20% more than that of B, who can complete a...

    Text Solution

    |

  6. A and B can do a work in 30 days, B and C do same work in 24 days. If ...

    Text Solution

    |

  7. P, Q and R are 3 small pumps fitted to a tank. S is a large pump fitte...

    Text Solution

    |

  8. P, Q and R are 3 small pumps fitted to a tank. S is a large pump fitte...

    Text Solution

    |

  9. Bibhor takes 3 hours to fetch as much water as Ahmed can fetch in 2 ho...

    Text Solution

    |

  10. Bibhor takes 3 hours to fetch as much water as Ahmed can fetch in 2 ho...

    Text Solution

    |

  11. The daily work of two men is equal to that of 3 women or that of 4 you...

    Text Solution

    |

  12. The daily work of two men is equal to that of 3 women or that of 4 you...

    Text Solution

    |

  13. A can complete a work in 20 days and B can complete the same work in 1...

    Text Solution

    |

  14. Time taken by A and B to complete a work is in the ratio 4 : 5. A alon...

    Text Solution

    |

  15. There are three pipes connected to the tank. Pipe A and pipe B can fil...

    Text Solution

    |

  16. Q is 50% more efficient than P, who completed a task in 45 days and R ...

    Text Solution

    |

  17. There are 2 inlet pipes and 1 outlet pipe assigned to fill a tank. If ...

    Text Solution

    |

  18. A ship is 108 km away from the shore when a leak appears on its bottom...

    Text Solution

    |

  19. There are four pipes connected to a tank - A, B, C and D. A & D are in...

    Text Solution

    |

  20. B alone can complete a piece of work in 36 days while D alone can comp...

    Text Solution

    |