Home
Class 14
MATHS
Working efficiency of A is 20% more than...

Working efficiency of A is 20% more than that of B, who can complete a work 'X' in 36 days.
B and C together started to complete the work 'X' and after 10 days they both left the work and then remaining work is done by A alone in 15 days.
A and C together started to complete another work 'Y' and after working for 12 days they both left the work and Remaining work is done by B alone in 16 days. If D first completed work 'X' and then completed work 'Y' in total 38 days.
It is given that efficiency of all, in completing work 'X' and work 'Y' is same.
A person E starts the work 'X' and leave after 12 days, then B and C complete the remaining work in 8 days. What is the ratio of number of days taken by A and E together to complete the work 'X' to the number of days taken by D, B and C together to complete the both work 'X' and 'Y'.

A

`3:5`

B

`5:3`

C

`8:7`

D

`1:2`

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's break it down into manageable parts: ### Step 1: Determine the efficiencies of A and B Given that the efficiency of A is 20% more than that of B, if we let the efficiency of B be \( E_B = 5 \), then: \[ E_A = E_B + 0.2 \times E_B = 5 + 1 = 6 \] Thus, the efficiencies are: - Efficiency of A = 6 - Efficiency of B = 5 ### Step 2: Calculate the total work for work X B can complete work X in 36 days. Therefore, the total work \( W_X \) can be calculated as: \[ W_X = E_B \times \text{Time taken by B} = 5 \times 36 = 180 \] ### Step 3: Find the efficiency of C B and C together worked for 10 days, and A completed the remaining work in 15 days. The total work done by A in 15 days is: \[ \text{Work done by A} = E_A \times \text{Time taken by A} = 6 \times 15 = 90 \] Thus, the work done by B and C together in 10 days is: \[ W_X - \text{Work done by A} = 180 - 90 = 90 \] Let the efficiency of C be \( E_C \). Therefore: \[ (E_B + E_C) \times 10 = 90 \] Substituting \( E_B = 5 \): \[ (5 + E_C) \times 10 = 90 \implies 5 + E_C = 9 \implies E_C = 4 \] ### Step 4: Calculate the total work for work Y A and C together worked for 12 days, and B completed the remaining work in 16 days. The total work done by A and C in 12 days is: \[ \text{Work done by A and C} = (E_A + E_C) \times 12 = (6 + 4) \times 12 = 120 \] Thus, the remaining work done by B in 16 days is: \[ W_Y - 120 = E_B \times 16 \implies W_Y - 120 = 5 \times 16 = 80 \implies W_Y = 200 \] ### Step 5: Calculate the efficiency of D D completed both works X and Y in 38 days: \[ \text{Total work} = W_X + W_Y = 180 + 200 = 380 \] Let the efficiency of D be \( E_D \): \[ E_D \times 38 = 380 \implies E_D = \frac{380}{38} = 10 \] ### Step 6: Determine the efficiency of E E starts work X and leaves after 12 days. The remaining work is completed by B and C in 8 days. The total work done by B and C in 8 days is: \[ (E_B + E_C) \times 8 = (5 + 4) \times 8 = 72 \] Thus, the work done by E in 12 days is: \[ W_X - 72 = 180 - 72 = 108 \] So, the efficiency of E can be calculated as: \[ E \times 12 = 108 \implies E = \frac{108}{12} = 9 \] ### Step 7: Calculate the ratio of days taken by A and E together to complete work X The combined efficiency of A and E is: \[ E_A + E_E = 6 + 9 = 15 \] The time taken by A and E together to complete work X is: \[ \text{Time} = \frac{W_X}{E_A + E_E} = \frac{180}{15} = 12 \text{ days} \] ### Step 8: Calculate the time taken by D, B, and C together to complete both works X and Y The combined efficiency of D, B, and C is: \[ E_D + E_B + E_C = 10 + 5 + 4 = 19 \] The total work for both X and Y is 380, so the time taken is: \[ \text{Time} = \frac{W_X + W_Y}{E_D + E_B + E_C} = \frac{380}{19} = 20 \text{ days} \] ### Step 9: Calculate the final ratio The required ratio of the number of days taken by A and E together to complete work X to the number of days taken by D, B, and C together to complete both works X and Y is: \[ \text{Ratio} = \frac{12}{20} = \frac{3}{5} \] ### Final Answer The ratio of the number of days taken by A and E together to complete work X to the number of days taken by D, B, and C together to complete both works X and Y is \( \frac{3}{5} \).
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PREVIOUS YEAR QUESTIONS |32 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PRELIMS QUESTIONS (LEVEL - 2) |40 Videos
  • SPEED, TIME AND DISTANCE

    ADDA247|Exercise Previous Year Questions|31 Videos
ADDA247-TIME AND WORK & PIPE AND CISTERN -MAINS QUESTIONS
  1. Working efficiency of A is 20% more than that of B, who can complete a...

    Text Solution

    |

  2. Working efficiency of A is 20% more than that of B, who can complete a...

    Text Solution

    |

  3. Working efficiency of A is 20% more than that of B, who can complete a...

    Text Solution

    |

  4. A and B can do a work in 30 days, B and C do same work in 24 days. If ...

    Text Solution

    |

  5. P, Q and R are 3 small pumps fitted to a tank. S is a large pump fitte...

    Text Solution

    |

  6. P, Q and R are 3 small pumps fitted to a tank. S is a large pump fitte...

    Text Solution

    |

  7. Bibhor takes 3 hours to fetch as much water as Ahmed can fetch in 2 ho...

    Text Solution

    |

  8. Bibhor takes 3 hours to fetch as much water as Ahmed can fetch in 2 ho...

    Text Solution

    |

  9. The daily work of two men is equal to that of 3 women or that of 4 you...

    Text Solution

    |

  10. The daily work of two men is equal to that of 3 women or that of 4 you...

    Text Solution

    |

  11. A can complete a work in 20 days and B can complete the same work in 1...

    Text Solution

    |

  12. Time taken by A and B to complete a work is in the ratio 4 : 5. A alon...

    Text Solution

    |

  13. There are three pipes connected to the tank. Pipe A and pipe B can fil...

    Text Solution

    |

  14. Q is 50% more efficient than P, who completed a task in 45 days and R ...

    Text Solution

    |

  15. There are 2 inlet pipes and 1 outlet pipe assigned to fill a tank. If ...

    Text Solution

    |

  16. A ship is 108 km away from the shore when a leak appears on its bottom...

    Text Solution

    |

  17. There are four pipes connected to a tank - A, B, C and D. A & D are in...

    Text Solution

    |

  18. B alone can complete a piece of work in 36 days while D alone can comp...

    Text Solution

    |

  19. Tap A and B together can fill a tank in 6 hours while B and C together...

    Text Solution

    |

  20. Dharam alone can complete a piece of work in 18 days. Deepak and Veer ...

    Text Solution

    |