Home
Class 14
MATHS
A can complete a work in 20 days and B c...

A can complete a work in 20 days and B can complete the same work in 16 days. C's work efficiency is `33(1)/(3)%` of the work efficiency of A and B together. In how many day A, B and C can complete the work if they work alternatively starting from A followed by B and C?

A

`18(4)/(5)`days

B

18 days

C

14 days

D

`19(4)/(5)`days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will follow these calculations: ### Step 1: Calculate the work done by A and B - A can complete the work in 20 days. Therefore, A's work efficiency is: \[ \text{Efficiency of A} = \frac{1}{20} \text{ (work/day)} \] - B can complete the work in 16 days. Therefore, B's work efficiency is: \[ \text{Efficiency of B} = \frac{1}{16} \text{ (work/day)} \] ### Step 2: Calculate the total efficiency of A and B - To find the total efficiency of A and B together, we need to find a common denominator: \[ \text{Efficiency of A} + \text{Efficiency of B} = \frac{1}{20} + \frac{1}{16} \] - The LCM of 20 and 16 is 80. Converting the efficiencies: \[ \frac{1}{20} = \frac{4}{80}, \quad \frac{1}{16} = \frac{5}{80} \] - Therefore, the total efficiency of A and B is: \[ \text{Total Efficiency of A and B} = \frac{4}{80} + \frac{5}{80} = \frac{9}{80} \text{ (work/day)} \] ### Step 3: Calculate C's efficiency - C's efficiency is given as \(33 \frac{1}{3}\%\) of the total efficiency of A and B: \[ C's \text{ efficiency} = \frac{33.33}{100} \times \frac{9}{80} = \frac{1}{3} \times \frac{9}{80} = \frac{3}{80} \text{ (work/day)} \] ### Step 4: Calculate the combined efficiency of A, B, and C - The combined efficiency of A, B, and C working together is: \[ \text{Total Efficiency of A, B, and C} = \frac{4}{80} + \frac{5}{80} + \frac{3}{80} = \frac{12}{80} = \frac{3}{20} \text{ (work/day)} \] ### Step 5: Determine the work done in one complete cycle - In one complete cycle (A, B, C), the work done is: \[ \text{Work done in one cycle} = \text{Efficiency of A} + \text{Efficiency of B} + \text{Efficiency of C} = \frac{4}{80} + \frac{5}{80} + \frac{3}{80} = \frac{12}{80} = \frac{3}{20} \] - The total work is 1 (the entire work), and in one cycle, they complete \(\frac{3}{20}\) of the work. ### Step 6: Calculate the number of cycles needed to complete the work - To find how many cycles are needed to complete the work: \[ \text{Number of cycles} = \frac{1}{\frac{3}{20}} = \frac{20}{3} \text{ cycles} \] ### Step 7: Calculate the total time taken for the cycles - Each cycle takes 3 days (A, B, C): \[ \text{Total days for complete cycles} = 3 \times \left\lfloor \frac{20}{3} \right\rfloor = 3 \times 6 = 18 \text{ days} \] ### Step 8: Calculate the remaining work after 18 days - In 18 days, they complete: \[ \text{Work done} = 6 \times \frac{3}{20} = \frac{18}{20} = \frac{9}{10} \] - Remaining work is: \[ 1 - \frac{9}{10} = \frac{1}{10} \] ### Step 9: Determine who works next and how much time it takes - On the 19th day, A works and completes: \[ \text{Work done by A on the 19th day} = \frac{1}{20} \] - Since \(\frac{1}{20} > \frac{1}{10}\), A will finish the remaining work on the 19th day. ### Final Answer - Therefore, the total time taken by A, B, and C to complete the work is: \[ 18 \text{ days} + \text{A's work on the 19th day} = 19 \frac{1}{5} \text{ days} \] - The answer is \(19 \frac{4}{5}\) days.
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PREVIOUS YEAR QUESTIONS |32 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PRELIMS QUESTIONS (LEVEL - 2) |40 Videos
  • SPEED, TIME AND DISTANCE

    ADDA247|Exercise Previous Year Questions|31 Videos
ADDA247-TIME AND WORK & PIPE AND CISTERN -MAINS QUESTIONS
  1. The daily work of two men is equal to that of 3 women or that of 4 you...

    Text Solution

    |

  2. The daily work of two men is equal to that of 3 women or that of 4 you...

    Text Solution

    |

  3. A can complete a work in 20 days and B can complete the same work in 1...

    Text Solution

    |

  4. Time taken by A and B to complete a work is in the ratio 4 : 5. A alon...

    Text Solution

    |

  5. There are three pipes connected to the tank. Pipe A and pipe B can fil...

    Text Solution

    |

  6. Q is 50% more efficient than P, who completed a task in 45 days and R ...

    Text Solution

    |

  7. There are 2 inlet pipes and 1 outlet pipe assigned to fill a tank. If ...

    Text Solution

    |

  8. A ship is 108 km away from the shore when a leak appears on its bottom...

    Text Solution

    |

  9. There are four pipes connected to a tank - A, B, C and D. A & D are in...

    Text Solution

    |

  10. B alone can complete a piece of work in 36 days while D alone can comp...

    Text Solution

    |

  11. Tap A and B together can fill a tank in 6 hours while B and C together...

    Text Solution

    |

  12. Dharam alone can complete a piece of work in 18 days. Deepak and Veer ...

    Text Solution

    |

  13. Efficiency of A is two times more than efficiency of B. Both A & B sta...

    Text Solution

    |

  14. Efficiency of A is two times more than efficiency of B. Both A & B sta...

    Text Solution

    |

  15. P and Q together can complete a work in 24 days, while Q and R working...

    Text Solution

    |

  16. A, B and C can do a work in 12,15 and 20 days respectively. All three ...

    Text Solution

    |

  17. X' men can complete a work in 4 days. '(X-2)' women can complete the s...

    Text Solution

    |

  18. Ravi who is 20% more efficiency than Manoj while 10% less efficient th...

    Text Solution

    |

  19. A work can be completed by A,B and C when working together in 12 days....

    Text Solution

    |

  20. 24 men can complete a work in 20 days. 36 women can do the same work i...

    Text Solution

    |