Home
Class 14
MATHS
Q is 50% more efficient than P, who comp...

Q is 50% more efficient than P, who completed a task in 45 days and R can do the same task in 7.5 days less than Q did. If P and Q start task together and after X days they left the task and R completed the remaining task in (X + 9) day. If Ratio between task done by (P + Q) together to task done by R alone is 1 : 2, Then find the value of X?

A

4.5 days

B

7 days

C

6 days

D

5 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will follow the information provided and derive the necessary equations. ### Step 1: Determine the efficiencies of P, Q, and R - Let the efficiency of P be \( E_P \). - Since Q is 50% more efficient than P, we have: \[ E_Q = E_P + 0.5E_P = 1.5E_P \] - Given that P takes 45 days to complete the task, the total work \( W \) can be expressed as: \[ W = E_P \times 45 \] ### Step 2: Calculate the efficiency of Q - From the efficiency relation: \[ E_Q = 1.5E_P \] - The time taken by Q to complete the same work is: \[ T_Q = \frac{W}{E_Q} = \frac{E_P \times 45}{1.5E_P} = 30 \text{ days} \] ### Step 3: Calculate the efficiency of R - R can complete the task in 7.5 days less than Q: \[ T_R = T_Q - 7.5 = 30 - 7.5 = 22.5 \text{ days} \] - Therefore, the efficiency of R is: \[ E_R = \frac{W}{T_R} = \frac{E_P \times 45}{22.5} = 2E_P \] ### Step 4: Set up the equation for work done - Let \( X \) be the number of days P and Q work together. - The work done by P and Q in \( X \) days is: \[ \text{Work}_{PQ} = (E_P + E_Q) \times X = (E_P + 1.5E_P) \times X = 2.5E_P \times X \] - The remaining work is: \[ \text{Remaining Work} = W - \text{Work}_{PQ} = E_P \times 45 - 2.5E_P \times X = E_P(45 - 2.5X) \] ### Step 5: Work done by R - R completes the remaining work in \( X + 9 \) days: \[ \text{Work}_{R} = E_R \times (X + 9) = 2E_P \times (X + 9) \] ### Step 6: Set up the ratio equation - According to the problem, the ratio of work done by P and Q together to the work done by R is 1:2: \[ \frac{\text{Work}_{PQ}}{\text{Work}_{R}} = \frac{1}{2} \] - Substituting the expressions we derived: \[ \frac{2.5E_P \times X}{2E_P \times (X + 9)} = \frac{1}{2} \] - Simplifying this gives: \[ \frac{2.5X}{2(X + 9)} = \frac{1}{2} \] - Cross-multiplying: \[ 2.5X \cdot 2 = 2(X + 9) \] \[ 5X = 2X + 18 \] - Rearranging gives: \[ 5X - 2X = 18 \implies 3X = 18 \implies X = 6 \] ### Final Answer Thus, the value of \( X \) is \( 6 \) days.
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PREVIOUS YEAR QUESTIONS |32 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PRELIMS QUESTIONS (LEVEL - 2) |40 Videos
  • SPEED, TIME AND DISTANCE

    ADDA247|Exercise Previous Year Questions|31 Videos
ADDA247-TIME AND WORK & PIPE AND CISTERN -MAINS QUESTIONS
  1. The daily work of two men is equal to that of 3 women or that of 4 you...

    Text Solution

    |

  2. A can complete a work in 20 days and B can complete the same work in 1...

    Text Solution

    |

  3. Time taken by A and B to complete a work is in the ratio 4 : 5. A alon...

    Text Solution

    |

  4. There are three pipes connected to the tank. Pipe A and pipe B can fil...

    Text Solution

    |

  5. Q is 50% more efficient than P, who completed a task in 45 days and R ...

    Text Solution

    |

  6. There are 2 inlet pipes and 1 outlet pipe assigned to fill a tank. If ...

    Text Solution

    |

  7. A ship is 108 km away from the shore when a leak appears on its bottom...

    Text Solution

    |

  8. There are four pipes connected to a tank - A, B, C and D. A & D are in...

    Text Solution

    |

  9. B alone can complete a piece of work in 36 days while D alone can comp...

    Text Solution

    |

  10. Tap A and B together can fill a tank in 6 hours while B and C together...

    Text Solution

    |

  11. Dharam alone can complete a piece of work in 18 days. Deepak and Veer ...

    Text Solution

    |

  12. Efficiency of A is two times more than efficiency of B. Both A & B sta...

    Text Solution

    |

  13. Efficiency of A is two times more than efficiency of B. Both A & B sta...

    Text Solution

    |

  14. P and Q together can complete a work in 24 days, while Q and R working...

    Text Solution

    |

  15. A, B and C can do a work in 12,15 and 20 days respectively. All three ...

    Text Solution

    |

  16. X' men can complete a work in 4 days. '(X-2)' women can complete the s...

    Text Solution

    |

  17. Ravi who is 20% more efficiency than Manoj while 10% less efficient th...

    Text Solution

    |

  18. A work can be completed by A,B and C when working together in 12 days....

    Text Solution

    |

  19. 24 men can complete a work in 20 days. 36 women can do the same work i...

    Text Solution

    |

  20. Anurag & Veer works to complete a task while Sameer works to destroy t...

    Text Solution

    |