Home
Class 14
MATHS
B alone can complete a piece of work in ...

B alone can complete a piece of work in 36 days while D alone can complete same piece of work in 25 days. C is 50 % more efficient than B and A is 20% less efficient than C. If all four starts working together (B & C are working with 56% & 20% more efficiency respectively than their usual efficiency), then in how many days the work will be completed?

A

A)12 days

B

B)18 days

C

C)15 days

D

D)6 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's break down the information given and calculate the required values. ### Step 1: Determine the efficiency of B and D - B can complete the work in 36 days. - D can complete the work in 25 days. The efficiency of a worker is inversely proportional to the time taken to complete the work. Thus, we can express their efficiencies as follows: - Efficiency of B (E_B) = 1/36 work/day - Efficiency of D (E_D) = 1/25 work/day To make calculations easier, we can convert these efficiencies to a common unit. Let's assume the total work is 3600 units (as calculated later). - Efficiency of B = 3600/36 = 100 units/day - Efficiency of D = 3600/25 = 144 units/day ### Step 2: Calculate the efficiency of C - C is 50% more efficient than B. Thus, the efficiency of C (E_C) can be calculated as: \[ E_C = E_B + 0.5 \times E_B = 1.5 \times E_B = 1.5 \times 100 = 150 \text{ units/day} \] ### Step 3: Calculate the efficiency of A - A is 20% less efficient than C. Thus, the efficiency of A (E_A) can be calculated as: \[ E_A = E_C - 0.2 \times E_C = 0.8 \times E_C = 0.8 \times 150 = 120 \text{ units/day} \] ### Step 4: Calculate the modified efficiencies of B and C - B is working with 56% more efficiency than usual: \[ \text{Modified efficiency of B} = E_B + 0.56 \times E_B = 1.56 \times E_B = 1.56 \times 100 = 156 \text{ units/day} \] - C is working with 20% more efficiency than usual: \[ \text{Modified efficiency of C} = E_C + 0.2 \times E_C = 1.2 \times E_C = 1.2 \times 150 = 180 \text{ units/day} \] ### Step 5: Calculate the total efficiency when A, B, C, and D work together Now, we can sum the efficiencies of A, B, C, and D: \[ \text{Total Efficiency} = E_A + \text{Modified efficiency of B} + \text{Modified efficiency of C} + E_D \] \[ = 120 + 156 + 180 + 144 = 600 \text{ units/day} \] ### Step 6: Calculate the total work We assumed the total work to be 3600 units. ### Step 7: Calculate the time taken to complete the work Using the formula: \[ \text{Time} = \frac{\text{Total Work}}{\text{Total Efficiency}} \] \[ \text{Time} = \frac{3600}{600} = 6 \text{ days} \] ### Final Answer The work will be completed in **6 days**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PREVIOUS YEAR QUESTIONS |32 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PRELIMS QUESTIONS (LEVEL - 2) |40 Videos
  • SPEED, TIME AND DISTANCE

    ADDA247|Exercise Previous Year Questions|31 Videos
ADDA247-TIME AND WORK & PIPE AND CISTERN -MAINS QUESTIONS
  1. The daily work of two men is equal to that of 3 women or that of 4 you...

    Text Solution

    |

  2. A can complete a work in 20 days and B can complete the same work in 1...

    Text Solution

    |

  3. Time taken by A and B to complete a work is in the ratio 4 : 5. A alon...

    Text Solution

    |

  4. There are three pipes connected to the tank. Pipe A and pipe B can fil...

    Text Solution

    |

  5. Q is 50% more efficient than P, who completed a task in 45 days and R ...

    Text Solution

    |

  6. There are 2 inlet pipes and 1 outlet pipe assigned to fill a tank. If ...

    Text Solution

    |

  7. A ship is 108 km away from the shore when a leak appears on its bottom...

    Text Solution

    |

  8. There are four pipes connected to a tank - A, B, C and D. A & D are in...

    Text Solution

    |

  9. B alone can complete a piece of work in 36 days while D alone can comp...

    Text Solution

    |

  10. Tap A and B together can fill a tank in 6 hours while B and C together...

    Text Solution

    |

  11. Dharam alone can complete a piece of work in 18 days. Deepak and Veer ...

    Text Solution

    |

  12. Efficiency of A is two times more than efficiency of B. Both A & B sta...

    Text Solution

    |

  13. Efficiency of A is two times more than efficiency of B. Both A & B sta...

    Text Solution

    |

  14. P and Q together can complete a work in 24 days, while Q and R working...

    Text Solution

    |

  15. A, B and C can do a work in 12,15 and 20 days respectively. All three ...

    Text Solution

    |

  16. X' men can complete a work in 4 days. '(X-2)' women can complete the s...

    Text Solution

    |

  17. Ravi who is 20% more efficiency than Manoj while 10% less efficient th...

    Text Solution

    |

  18. A work can be completed by A,B and C when working together in 12 days....

    Text Solution

    |

  19. 24 men can complete a work in 20 days. 36 women can do the same work i...

    Text Solution

    |

  20. Anurag & Veer works to complete a task while Sameer works to destroy t...

    Text Solution

    |