Home
Class 14
MATHS
P and Q together can complete a work in ...

P and Q together can complete a work in 24 days, while Q and R working together can complete the same job in 32 days. P and Q started the work and did it for 8 days, after that P left the work and R joined Q and after 12 more days, Q also left the work. Then, the remaining work was completed by R in 28 days. Find in how many days R will complete the work alone?

A

96 days

B

72 days

C

108 days

D

90 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will break down the information provided and calculate the required values systematically. ### Step 1: Calculate Total Work P and Q together can complete the work in 24 days. Therefore, their combined efficiency is: \[ \text{Efficiency of P + Q} = \frac{1}{24} \text{ work/day} \] Similarly, Q and R can complete the work in 32 days, so their combined efficiency is: \[ \text{Efficiency of Q + R} = \frac{1}{32} \text{ work/day} \] To find the total work, we can use the least common multiple (LCM) of the two time periods: \[ \text{Total Work} = \text{LCM}(24, 32) = 96 \text{ units of work} \] ### Step 2: Calculate Individual Efficiencies From the efficiencies calculated: - Let the efficiency of P be \( p \), Q be \( q \), and R be \( r \). - We have: \[ p + q = \frac{96}{24} = 4 \text{ (units of work/day)} \] \[ q + r = \frac{96}{32} = 3 \text{ (units of work/day)} \] ### Step 3: Set Up Equations Now, we can set up the equations: 1. \( p + q = 4 \) 2. \( q + r = 3 \) From the first equation, we can express \( p \) in terms of \( q \): \[ p = 4 - q \] Substituting \( p \) into the second equation: \[ (4 - q) + r = 3 \] This simplifies to: \[ r = 3 - 4 + q = q - 1 \] ### Step 4: Calculate Work Done by P and Q P and Q work together for 8 days: \[ \text{Work done by P + Q in 8 days} = 8 \times 4 = 32 \text{ units} \] ### Step 5: Calculate Remaining Work The total work is 96 units, so the remaining work after P and Q have worked for 8 days is: \[ \text{Remaining Work} = 96 - 32 = 64 \text{ units} \] ### Step 6: Calculate Work Done by Q and R Next, Q and R work together for 12 days: \[ \text{Work done by Q + R in 12 days} = 12 \times 3 = 36 \text{ units} \] ### Step 7: Calculate Remaining Work After Q and R After Q and R have worked for 12 days, the remaining work is: \[ \text{Remaining Work} = 64 - 36 = 28 \text{ units} \] ### Step 8: Calculate Work Done by R R completes the remaining 28 units of work in 28 days: \[ \text{Efficiency of R} = \frac{28 \text{ units}}{28 \text{ days}} = 1 \text{ unit of work/day} \] ### Step 9: Calculate Time Taken by R Alone To find out how many days R will take to complete the entire work alone: \[ \text{Time taken by R} = \frac{\text{Total Work}}{\text{Efficiency of R}} = \frac{96}{1} = 96 \text{ days} \] ### Final Answer R will complete the work alone in **96 days**.
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PREVIOUS YEAR QUESTIONS |32 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PRELIMS QUESTIONS (LEVEL - 2) |40 Videos
  • SPEED, TIME AND DISTANCE

    ADDA247|Exercise Previous Year Questions|31 Videos
ADDA247-TIME AND WORK & PIPE AND CISTERN -MAINS QUESTIONS
  1. The daily work of two men is equal to that of 3 women or that of 4 you...

    Text Solution

    |

  2. A can complete a work in 20 days and B can complete the same work in 1...

    Text Solution

    |

  3. Time taken by A and B to complete a work is in the ratio 4 : 5. A alon...

    Text Solution

    |

  4. There are three pipes connected to the tank. Pipe A and pipe B can fil...

    Text Solution

    |

  5. Q is 50% more efficient than P, who completed a task in 45 days and R ...

    Text Solution

    |

  6. There are 2 inlet pipes and 1 outlet pipe assigned to fill a tank. If ...

    Text Solution

    |

  7. A ship is 108 km away from the shore when a leak appears on its bottom...

    Text Solution

    |

  8. There are four pipes connected to a tank - A, B, C and D. A & D are in...

    Text Solution

    |

  9. B alone can complete a piece of work in 36 days while D alone can comp...

    Text Solution

    |

  10. Tap A and B together can fill a tank in 6 hours while B and C together...

    Text Solution

    |

  11. Dharam alone can complete a piece of work in 18 days. Deepak and Veer ...

    Text Solution

    |

  12. Efficiency of A is two times more than efficiency of B. Both A & B sta...

    Text Solution

    |

  13. Efficiency of A is two times more than efficiency of B. Both A & B sta...

    Text Solution

    |

  14. P and Q together can complete a work in 24 days, while Q and R working...

    Text Solution

    |

  15. A, B and C can do a work in 12,15 and 20 days respectively. All three ...

    Text Solution

    |

  16. X' men can complete a work in 4 days. '(X-2)' women can complete the s...

    Text Solution

    |

  17. Ravi who is 20% more efficiency than Manoj while 10% less efficient th...

    Text Solution

    |

  18. A work can be completed by A,B and C when working together in 12 days....

    Text Solution

    |

  19. 24 men can complete a work in 20 days. 36 women can do the same work i...

    Text Solution

    |

  20. Anurag & Veer works to complete a task while Sameer works to destroy t...

    Text Solution

    |