Home
Class 14
MATHS
X' men can complete a work in 4 days. '(...

X' men can complete a work in 4 days. '(X-2)' women can complete the same work in 8 days, while ratio of efficiency of man to woman is 3 : 2. If `'(x)/(2)'` men & '(X - 2)' women started the work & worked for only 2 days then, how many women should replace to men to complete the remaining work in three days?

A

2 women

B

8 women

C

6 women

D

4 women

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will break down the information given and calculate accordingly. ### Step 1: Calculate Total Work Done by Men and Women Given: - \( X \) men can complete the work in 4 days. - \( (X - 2) \) women can complete the same work in 8 days. - The efficiency ratio of men to women is \( 3:2 \). Let the efficiency of one man be \( M = 3k \) and the efficiency of one woman be \( W = 2k \). **Total work done by men:** \[ \text{Total Work} = \text{Number of Men} \times \text{Efficiency of Men} \times \text{Time} \] \[ = X \times 3k \times 4 = 12Xk \] **Total work done by women:** \[ \text{Total Work} = \text{Number of Women} \times \text{Efficiency of Women} \times \text{Time} \] \[ = (X - 2) \times 2k \times 8 = 16(X - 2)k \] Since both expressions represent the same total work, we can set them equal: \[ 12Xk = 16(X - 2)k \] ### Step 2: Simplify the Equation Dividing both sides by \( k \) (assuming \( k \neq 0 \)): \[ 12X = 16(X - 2) \] Expanding the right side: \[ 12X = 16X - 32 \] Rearranging gives: \[ 32 = 16X - 12X \] \[ 32 = 4X \] \[ X = 8 \] ### Step 3: Calculate the Number of Men and Women Now substituting \( X \) back: - Number of Men = \( X = 8 \) - Number of Women = \( X - 2 = 6 \) ### Step 4: Work Done in 2 Days Now, \( \frac{X}{2} = \frac{8}{2} = 4 \) men and \( (X - 2) = 6 \) women start the work. **Daily work done:** \[ \text{Work by Men in 1 day} = 4 \times 3 = 12 \] \[ \text{Work by Women in 1 day} = 6 \times 2 = 12 \] \[ \text{Total Work in 1 day} = 12 + 12 = 24 \] **Work done in 2 days:** \[ \text{Total Work in 2 days} = 24 \times 2 = 48 \] ### Step 5: Calculate Remaining Work **Total Work:** \[ \text{Total Work} = 12Xk = 12 \times 8k = 96k \] **Remaining Work:** \[ \text{Remaining Work} = 96k - 48 = 48k \] ### Step 6: Work Required in 3 Days To complete the remaining work in 3 days: \[ \text{Work required per day} = \frac{48k}{3} = 16k \] ### Step 7: Determine How Many Women are Needed Let \( Y \) be the number of women replacing men. The efficiency of \( Y \) women is: \[ \text{Work done by Y women in 1 day} = Y \times 2k \] Setting the total work done in a day to 16k: \[ Y \times 2k = 16k \] Dividing both sides by \( 2k \): \[ Y = 8 \] ### Step 8: Calculate the Number of Women to Replace Initially, there were 6 women. To find how many women need to be added: \[ \text{Women to replace} = Y - 6 = 8 - 6 = 2 \] ### Final Answer **The number of women that should replace men to complete the remaining work in three days is 2.** ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PREVIOUS YEAR QUESTIONS |32 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PRELIMS QUESTIONS (LEVEL - 2) |40 Videos
  • SPEED, TIME AND DISTANCE

    ADDA247|Exercise Previous Year Questions|31 Videos
ADDA247-TIME AND WORK & PIPE AND CISTERN -MAINS QUESTIONS
  1. The daily work of two men is equal to that of 3 women or that of 4 you...

    Text Solution

    |

  2. A can complete a work in 20 days and B can complete the same work in 1...

    Text Solution

    |

  3. Time taken by A and B to complete a work is in the ratio 4 : 5. A alon...

    Text Solution

    |

  4. There are three pipes connected to the tank. Pipe A and pipe B can fil...

    Text Solution

    |

  5. Q is 50% more efficient than P, who completed a task in 45 days and R ...

    Text Solution

    |

  6. There are 2 inlet pipes and 1 outlet pipe assigned to fill a tank. If ...

    Text Solution

    |

  7. A ship is 108 km away from the shore when a leak appears on its bottom...

    Text Solution

    |

  8. There are four pipes connected to a tank - A, B, C and D. A & D are in...

    Text Solution

    |

  9. B alone can complete a piece of work in 36 days while D alone can comp...

    Text Solution

    |

  10. Tap A and B together can fill a tank in 6 hours while B and C together...

    Text Solution

    |

  11. Dharam alone can complete a piece of work in 18 days. Deepak and Veer ...

    Text Solution

    |

  12. Efficiency of A is two times more than efficiency of B. Both A & B sta...

    Text Solution

    |

  13. Efficiency of A is two times more than efficiency of B. Both A & B sta...

    Text Solution

    |

  14. P and Q together can complete a work in 24 days, while Q and R working...

    Text Solution

    |

  15. A, B and C can do a work in 12,15 and 20 days respectively. All three ...

    Text Solution

    |

  16. X' men can complete a work in 4 days. '(X-2)' women can complete the s...

    Text Solution

    |

  17. Ravi who is 20% more efficiency than Manoj while 10% less efficient th...

    Text Solution

    |

  18. A work can be completed by A,B and C when working together in 12 days....

    Text Solution

    |

  19. 24 men can complete a work in 20 days. 36 women can do the same work i...

    Text Solution

    |

  20. Anurag & Veer works to complete a task while Sameer works to destroy t...

    Text Solution

    |