Home
Class 14
MATHS
A work can be completed by A,B and C whe...

A work can be completed by A,B and C when working together in 12 days. If B working alone can completes 25% of the same work in 8 days and ratio of efficiency of C to that of A is 1:4. Find in how many days A and B can complete the same work together? (in days)

A

`12(5)/(7)`

B

`13(5)/(7)`

C

`14(5)/(7)`

D

`11(5)/(7)`

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's break it down: ### Step 1: Determine the total work done by A, B, and C together Given that A, B, and C can complete the work together in 12 days, we can calculate the total work in terms of efficiency. Total work = Efficiency × Time Let the total work be W. Since they complete the work in 12 days, we have: \[ W = \text{Efficiency of (A + B + C)} \times 12 \] ### Step 2: Calculate B's efficiency It is given that B can complete 25% of the work in 8 days. 25% of the work means \( \frac{1}{4} \) of W. If B completes \( \frac{1}{4} \) of the work in 8 days, then the total work W can be calculated as follows: B's efficiency = \( \frac{1/4 \text{ of W}}{8 \text{ days}} = \frac{W}{32} \) Thus, B's efficiency = \( \frac{W}{32} \) ### Step 3: Calculate the efficiency of A + B + C Since A, B, and C together complete the work in 12 days, their combined efficiency is: \[ \text{Efficiency of (A + B + C)} = \frac{W}{12} \] ### Step 4: Calculate the efficiency of A + C Using the efficiency of B calculated in Step 2, we can find the efficiency of A + C: \[ \text{Efficiency of (A + C)} = \text{Efficiency of (A + B + C)} - \text{Efficiency of B} \] \[ \text{Efficiency of (A + C)} = \frac{W}{12} - \frac{W}{32} \] To perform this subtraction, we need a common denominator. The LCM of 12 and 32 is 96. Converting both fractions: \[ \frac{W}{12} = \frac{8W}{96} \] \[ \frac{W}{32} = \frac{3W}{96} \] Now, subtract: \[ \text{Efficiency of (A + C)} = \frac{8W}{96} - \frac{3W}{96} = \frac{5W}{96} \] ### Step 5: Determine the ratio of efficiencies of A and C It is given that the ratio of the efficiency of C to A is 1:4. Let the efficiency of C be x. Then the efficiency of A will be 4x. Thus, we can write: \[ \text{Efficiency of (A + C)} = 4x + x = 5x \] From Step 4, we have: \[ 5x = \frac{5W}{96} \] Thus, we can find x: \[ x = \frac{W}{96} \] So, the efficiencies are: - Efficiency of A = \( 4x = \frac{4W}{96} = \frac{W}{24} \) - Efficiency of C = \( x = \frac{W}{96} \) ### Step 6: Calculate the efficiency of A + B Now, we can find the combined efficiency of A and B: \[ \text{Efficiency of (A + B)} = \text{Efficiency of A} + \text{Efficiency of B} \] \[ \text{Efficiency of (A + B)} = \frac{W}{24} + \frac{W}{32} \] Again, we need a common denominator (LCM of 24 and 32 is 96): \[ \frac{W}{24} = \frac{4W}{96} \] \[ \frac{W}{32} = \frac{3W}{96} \] Now, adding: \[ \text{Efficiency of (A + B)} = \frac{4W}{96} + \frac{3W}{96} = \frac{7W}{96} \] ### Step 7: Calculate the time taken by A and B to complete the work together Now, we can find the time taken by A and B to complete the work: \[ \text{Time} = \frac{\text{Total Work}}{\text{Efficiency of (A + B)}} \] \[ \text{Time} = \frac{W}{\frac{7W}{96}} = \frac{96}{7} \] Thus, the time taken by A and B to complete the work together is: \[ \text{Time} = 13 \frac{5}{7} \text{ days} \] ### Final Answer A and B can complete the work together in **13 days and 5/7 days**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PREVIOUS YEAR QUESTIONS |32 Videos
  • TIME AND WORK & PIPE AND CISTERN

    ADDA247|Exercise PRELIMS QUESTIONS (LEVEL - 2) |40 Videos
  • SPEED, TIME AND DISTANCE

    ADDA247|Exercise Previous Year Questions|31 Videos
ADDA247-TIME AND WORK & PIPE AND CISTERN -MAINS QUESTIONS
  1. The daily work of two men is equal to that of 3 women or that of 4 you...

    Text Solution

    |

  2. A can complete a work in 20 days and B can complete the same work in 1...

    Text Solution

    |

  3. Time taken by A and B to complete a work is in the ratio 4 : 5. A alon...

    Text Solution

    |

  4. There are three pipes connected to the tank. Pipe A and pipe B can fil...

    Text Solution

    |

  5. Q is 50% more efficient than P, who completed a task in 45 days and R ...

    Text Solution

    |

  6. There are 2 inlet pipes and 1 outlet pipe assigned to fill a tank. If ...

    Text Solution

    |

  7. A ship is 108 km away from the shore when a leak appears on its bottom...

    Text Solution

    |

  8. There are four pipes connected to a tank - A, B, C and D. A & D are in...

    Text Solution

    |

  9. B alone can complete a piece of work in 36 days while D alone can comp...

    Text Solution

    |

  10. Tap A and B together can fill a tank in 6 hours while B and C together...

    Text Solution

    |

  11. Dharam alone can complete a piece of work in 18 days. Deepak and Veer ...

    Text Solution

    |

  12. Efficiency of A is two times more than efficiency of B. Both A & B sta...

    Text Solution

    |

  13. Efficiency of A is two times more than efficiency of B. Both A & B sta...

    Text Solution

    |

  14. P and Q together can complete a work in 24 days, while Q and R working...

    Text Solution

    |

  15. A, B and C can do a work in 12,15 and 20 days respectively. All three ...

    Text Solution

    |

  16. X' men can complete a work in 4 days. '(X-2)' women can complete the s...

    Text Solution

    |

  17. Ravi who is 20% more efficiency than Manoj while 10% less efficient th...

    Text Solution

    |

  18. A work can be completed by A,B and C when working together in 12 days....

    Text Solution

    |

  19. 24 men can complete a work in 20 days. 36 women can do the same work i...

    Text Solution

    |

  20. Anurag & Veer works to complete a task while Sameer works to destroy t...

    Text Solution

    |