Fifteen men take 10 days to complete a job working 12 hours a day.How many hours a day should 10 men work to complete the job in 20 days ?

Text Solution

AI Generated Solution

To solve the problem step by step, we will use the concept of work done, which is calculated using the formula: **Work = Number of Men × Number of Days × Number of Hours per Day** ### Step 1: Calculate the Total Work Done First, we calculate the total work done by 15 men in 10 days, working 12 hours a day. \[ ...
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK, PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise TEST YOUR CONCEPTS (Very Short Answer Type Questions)|30 Videos
  • TIME AND WORK, PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise Short Answer Type Questions|15 Videos
  • TIME AND WORK PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise CONCEPT APPLICATION (LEVEL-3)|7 Videos

Similar Questions

Explore conceptually related problems

Fifteen men take 10 days to complete a job working 12hours a day. How many hours in a day should 10 men work to complete the same job in 20 days?

10 men working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days.

10 men, working. 6 hours a day can compJete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days?

Fifteen men take 30 days to complete a piece of work, working 8 hours a day. Find the time taken by 30 men to complete 5 times as much work, working 10 hours a day.

A man working 8 hours a day takes 5 days to complete a project. How many hours a day must he work to complete. It in 4 days?