Home
Class 8
MATHS
A piece of work can be done by 16 men in...

A piece of work can be done by 16 men in 8 days working 12 hours a day. How many men are needed to complete another work, which is three times the first one, in 24 days working 8 hours a days ?

Text Solution

Verified by Experts

Using the formula,`(M_(1)D_(1)H_(1))/(W_(1))=(M_(2)D_(2)H_(2))/(W_(2))`
Let `W_(1)=x` and `W_(2)=3x`
`M_(1)`=16,`H_(1)`=12,`D_(1)`=8
`H_(2)`=8,`D_(2)`=24
`:. (16xx8xx12)/(x)=(M_(2)xx24xx8)/(3x)`
`implies M_(2)=24` men.
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK, PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise TEST YOUR CONCEPTS (Very Short Answer Type Questions)|30 Videos
  • TIME AND WORK, PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise Short Answer Type Questions|15 Videos
  • TIME AND WORK PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise CONCEPT APPLICATION (LEVEL-3)|7 Videos

Similar Questions

Explore conceptually related problems

A piece of work can be done by 16 man in 8 days working 12 hours a day. How many men ar needed to complete another work,which is three times the first one, in 24n days working 8 hourse, a day?

20 men can do a work in 35 days. How many men are needed to complete the same work in 25 days.

A piece of work in be done by 64 men in 17 days working for 9 hourse per day. In how many days can 34 men do a piece of work (8)/(3) times of the previous one one on working 8 hore per day ?

12 men can do a piece of work in 24 days. How many days are needed to complete the work, if 8 men are engaged in the same work ?

If 25 men can do a piece of work in 36 days working 10 hours a day, then how many men are required to complete the work working 6 hours a day in 20 days?

Fifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?

Fifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?

12 men can complete a work in 30 days by working 9 hours a day. What is the number of men required to complete 10 times of this work in 24 days by working 5 hours a day ?