A and B can do a piece of work in 6 days and 9 days respectively, they work on alternative days starting with A on the first day. In how many days will the work be completed ?

Text Solution

Verified by Experts

Since they work on alternate days, let us consider a period of two days.
In a period of two days, work done by A and B
`=1//6+1//9=5//18`
If we consider 3 such time periods (we are considering 3 periods because in the fraction 5/18, the numerator 5 goes 3 times in the denominator 18),
Work done `=3xx(5//18)=15//18`
Remaining work `=3//18=1//16`
Now it is A's turn, since 3 whole numbers of periods are over.
Time taken by A to finish 1/16th of the work is one day.
So, total time taken `=(3xx2)+1=7` days.
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK, PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise TEST YOUR CONCEPTS (Very Short Answer Type Questions)|30 Videos
  • TIME AND WORK, PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise Short Answer Type Questions|15 Videos
  • TIME AND WORK PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise CONCEPT APPLICATION (LEVEL-3)|7 Videos

Similar Questions

Explore conceptually related problems

A and B can complete a piece of work in 4 days and 8 days, respctively. They work on alternate days and A starts the work. In how work in may days will the work be completed

A and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?

A and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?

A and B can do a piece of work in 20 days and 30 days respectively. A start the work and they do this work in alternate days. In how many days will this work be completed ?

Fatima and Zahira can do a piece of work in 12 days and 15 days respectively. If they work for alternate day and Fatima starts the work first, then in how many days the work will be completed?