A,B and C can do a piece of work in 4 days, 5 days and 7 days respectively. They get ₹ 415 for completing the job. If A, B and C have worked together to complete the job, what is A's share?

Text Solution

Verified by Experts

Since they work for the same number of days, the ratio in which they share the money is the ratio of work done per day.
i.e. `1//4:1//5:1//7=35:28:20` Hence A's share is `(38/83)xx415=₹ 175`.
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK, PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise TEST YOUR CONCEPTS (Very Short Answer Type Questions)|30 Videos
  • TIME AND WORK, PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise Short Answer Type Questions|15 Videos
  • TIME AND WORK PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise CONCEPT APPLICATION (LEVEL-3)|7 Videos

Similar Questions

Explore conceptually related problems

A, B and C can do a piece of work in 4 days , 5 days, and 7 days, respectively get Rs.415 for completing the job. If A,B and C have worked together to complete the job, what is A's share?

A and B can do a piece of work in 50 days and 40 days respectively. If together they earned ₹ 450 by completing the work , then what is the share of B?

A, B and C can complete a piece of work in 10 days, 20 days and 25 days, respectively. If they tak 40 days to complete a piece of work, then in how many days can C alone complete the work ?