A is twice as fast as B and together the...

A is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, let's break it down step by step. ### Step 1: Define the work rates of A and B Let the work rate of B be \( x \) (work done per day). Since A is twice as fast as B, the work rate of A will be \( 2x \). ### Step 2: Calculate the combined work rate of A and B When A and B work together, their combined work rate is: \[ \text{Combined work rate} = x + 2x = 3x \] ### Step 3: Determine the total work done If A and B together can complete the work in 20 days, the total work can be expressed as: \[ \text{Total work} = \text{Combined work rate} \times \text{Time} = 3x \times 20 = 60x \] ### Step 4: Find the time taken by A alone to complete the work Now, we need to find out how many days A alone will take to complete the total work of \( 60x \). Since A's work rate is \( 2x \), the time taken by A to complete the work is: \[ \text{Time taken by A} = \frac{\text{Total work}}{\text{A's work rate}} = \frac{60x}{2x} = 30 \text{ days} \] ### Conclusion Thus, A alone can complete the work in **30 days**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK, PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise Short Answer Type Questions|15 Videos
  • TIME AND WORK, PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise Essay Type Question|5 Videos
  • TIME AND WORK, PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise CONCEPT APPLICATION (LEVEL-3)|7 Videos
  • TIME AND WORK PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise CONCEPT APPLICATION (LEVEL-3)|7 Videos

Similar Questions

Explore conceptually related problems

A works 3 times as fast as B. If B can complete a work in 60 days, then in how many days can A and B together complete the same work ?

Mukesh and Dinesh together can complete a work in 120 days. Mukesh alone can complete the work in 150 days. In how many days can Dinesh alone complete the work?

1 man and 1 woman together can complete a piece of work in 8 days. A man alone can complete the work in 10 days. In how many days, can one woman alone complete the work?

Anil, Bhuvan and Chirag together can complete a work in 35 days. Anil and Chirag together can complete the same work in 60 days. In how many days Bhuvan alone can complete the same work?

PEARSON IIT JEE FOUNDATION-TIME AND WORK, PIPES AND CISTERNS-TEST YOUR CONCEPTS (Very Short Answer Type Questions)
  1. A pipe can fill a tank in 4 hours and another pipe can empty the same ...

    Text Solution

    |

  2. A, B and C can do a piece of work in 3, 4 and 6 days respectively. The...

    Text Solution

    |

  3. A is twice as fast as B and together they can complete a work in 20 da...

    Text Solution

    |

  4. If 6 boys can eat 6 apples 6 minutes then, 3 boys can eat 3 apples in ...

    Text Solution

    |

  5. Working together, X and Y can do a piece of work in 12 days, Y and Z ...

    Text Solution

    |

  6. A and B can do 1/2 and 2/3rd parts of a work in a given time. The rati...

    Text Solution

    |

  7. In a unit time, the work done by 3 men and 5 women is equal to the wor...

    Text Solution

    |

  8. A can type 30 words in 1 minutes and B can type 20 words in 1 minute. ...

    Text Solution

    |

  9. Twelve men can make 24 articles in 6 days. How many articles can 3 men...

    Text Solution

    |

  10. In a unit time, the work done by 3 men is equal to the work done by 6 ...

    Text Solution

    |

  11. X can knit 60 baskets in 8 day with the help of Y, who is having the s...

    Text Solution

    |

  12. X, Y and Z can complete a piece of work in 10 days. X and Y can do it ...

    Text Solution

    |

  13. A can complete a piece of work working along with B in 20 days. If he ...

    Text Solution

    |

  14. Tap A can fill a tank of 1000 litres capacity in 14 hours. It can fill...

    Text Solution

    |

  15. X persons can complete a work in Y days. Then, 3X persons can complete...

    Text Solution

    |

  16. Thirty men can lay a road of length 8 km in 8 days. The number of men...

    Text Solution

    |

  17. The ratio of the number of days required by A,B and C to do a piece of...

    Text Solution

    |

  18. By working 8 hours a day. A can complete a work in 10 day. If the redu...

    Text Solution

    |

  19. Satish, Goel and Khan can do a particular job in 24,36 and 48 days res...

    Text Solution

    |

  20. Two persons X and Y together can do a particular job in 36 days. If X'...

    Text Solution

    |