Murali and Sai can complete a job in 20...

Murali and Sai can complete a job in 20 days and 30 days respectively. Two days after they start the job, Murali leaves and Sai completes the remining job. In how many days can Sai complete the remaining job ?

A

20

B

25

C

15

D

18

Text Solution

Verified by Experts

The correct Answer is:
B

Part of the job completed by Murali and Sai in 2 days `=2((1)/(20)+(1)/(30))=(1)/(6)`
Remaining part`=(5)/(6)`
Time taken by Sai to complete the remaining part `=(5)/(6)(30)=25` days.
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK, PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise CONCEPT APPLICATION (LEVEL-3)|7 Videos
  • TIME AND WORK, PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise CONCEPT APPLICATION (LEVEL-1)|33 Videos
  • TIME AND WORK PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise CONCEPT APPLICATION (LEVEL-3)|7 Videos

Similar Questions

Explore conceptually related problems

M and N can complete a job in 120 days and 180 days respectively. M started the job and after 60 days N joined M and they completed the remaining part of the job working together.In how many days was the job completed?

M and N can complete a job in 120 days and 180 days respectively. M started the job and after 60 days N joined M and they completed the remaining part of the job working together.In how many days was the job completed?

M and N can complete a job in 18 days and 20 days, respectively. They worked on it on alternative days starting with M. Find the time taken to comlete it (in day)

If 20 men take 30 days to complete a job, in how many days can 25 men complete the job?

If 20 men take 30 days to complete a job, in how many days can 25 men complete the job?

If 20 men take 30 days to complete a job, in how many days can 25 men complete the job?

P,Q and R can complete a job in 20 days, 30 and 40 days respectiely. They started working on it. Q and R left afte working for certain number of days and P alone completed the remaing work 7 days. Find the time taken to complete the job (in days)

PEARSON IIT JEE FOUNDATION-TIME AND WORK, PIPES AND CISTERNS-CONCEPT APPLICATION (LEVEL-2)
  1. Rishikesh and Mukesh can individually complete a piece of work in 18 ...

    Text Solution

    |

  2. A can work twice as fast as B.A. and C together can work three times a...

    Text Solution

    |

  3. P and Q can individually complete a piece of work in 15 and 25 days re...

    Text Solution

    |

  4. Two taps A and B can fill a tank in 12 minutes and 20 minutes respecti...

    Text Solution

    |

  5. Wages for 30 women amounts to ₹ 60,000 in 36 days. If a man earns dou...

    Text Solution

    |

  6. 6 men and 9 women can do a piece of work in 4 days.4 men and 3 women c...

    Text Solution

    |

  7. A,B andC can complete a piece of work in 6,12 and 18 days respectively...

    Text Solution

    |

  8. A and B can complete a piece of work in 10 and 15 days respectively. B...

    Text Solution

    |

  9. P worked on a job for 4 hours and then Q joined him. After 8 more hour...

    Text Solution

    |

  10. P,Q and R work together to complete a piece of work in x days. P and R...

    Text Solution

    |

  11. P,Q and R can do a piece of work in 18 days, 36 days and 54 day respec...

    Text Solution

    |

  12. Pipes A, B and C can fill an empty tank in 12 minutes, 24 minutes and ...

    Text Solution

    |

  13. X,Y and Z can complete a job in 24 days, 32 days and 48 days respectiv...

    Text Solution

    |

  14. P and Q can complete a job in 6 days and 7 days respectively. They wor...

    Text Solution

    |

  15. M and N can complete a job in 120 days and 180 days respectively. M st...

    Text Solution

    |

  16. B can do a job twice as fast as A and half as fast as C.A.B. and C tog...

    Text Solution

    |

  17. Ten boys or twenty girls can complete a job in 10 days. In how many da...

    Text Solution

    |

  18. Murali and Sai can complete a job in 20 days and 30 days respectively...

    Text Solution

    |

  19. Y can complete a job half as fast as X and twice as fast as Z,X,Y and ...

    Text Solution

    |

  20. Five men or ten women can complete a job in 20 days. In how many days ...

    Text Solution

    |