Home
Class 14
MATHS
A and B can do a piece of work in 40 da...

A and B can do a piece of work in 40 days and 50 days , respectively. Both begin together but after a certain time , A leaves off . In this case B finished the remaining work in 20 days . After how many days did A leave ?

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first determine the work done by A and B, then calculate how long A worked before leaving. ### Step 1: Determine the work rates of A and B - A can complete the work in 40 days, so A's work rate is \( \frac{1}{40} \) of the work per day. - B can complete the work in 50 days, so B's work rate is \( \frac{1}{50} \) of the work per day. **Hint:** Work rate is calculated as the total work divided by the time taken to complete that work. ### Step 2: Set up the equation for the total work done Let A work for \( x \) days before leaving. In those \( x \) days, A and B work together. The amount of work done by A in \( x \) days is: \[ \text{Work done by A} = A's \text{ rate} \times x = \frac{x}{40} \] The amount of work done by B in \( x \) days is: \[ \text{Work done by B} = B's \text{ rate} \times x = \frac{x}{50} \] Thus, the total work done by A and B together in \( x \) days is: \[ \text{Total work done in } x \text{ days} = \frac{x}{40} + \frac{x}{50} \] **Hint:** To combine fractions, find a common denominator. ### Step 3: Find a common denominator and simplify The least common multiple of 40 and 50 is 200. Therefore, we can rewrite the work done as: \[ \frac{x}{40} = \frac{5x}{200} \] \[ \frac{x}{50} = \frac{4x}{200} \] So, the total work done in \( x \) days is: \[ \frac{5x}{200} + \frac{4x}{200} = \frac{9x}{200} \] **Hint:** Combine the fractions by adding the numerators while keeping the common denominator. ### Step 4: Calculate the remaining work done by B After A leaves, B finishes the remaining work in 20 days. The amount of work done by B in 20 days is: \[ \text{Work done by B in 20 days} = B's \text{ rate} \times 20 = \frac{20}{50} = \frac{2}{5} \] **Hint:** Remember that the total work is considered as 1 unit. ### Step 5: Set up the equation for total work The total work is 1 unit, so we can set up the equation: \[ \text{Total work} = \text{Work done by A and B in } x \text{ days} + \text{Work done by B in 20 days} \] \[ 1 = \frac{9x}{200} + \frac{2}{5} \] **Hint:** Convert \( \frac{2}{5} \) to have a common denominator with \( \frac{9x}{200} \). ### Step 6: Solve for \( x \) Convert \( \frac{2}{5} \) to a fraction with a denominator of 200: \[ \frac{2}{5} = \frac{80}{200} \] Now, substitute back into the equation: \[ 1 = \frac{9x}{200} + \frac{80}{200} \] \[ 1 = \frac{9x + 80}{200} \] Multiply both sides by 200: \[ 200 = 9x + 80 \] Now, isolate \( x \): \[ 9x = 200 - 80 \] \[ 9x = 120 \] \[ x = \frac{120}{9} = \frac{40}{3} \] ### Step 7: Convert \( x \) into days To convert \( \frac{40}{3} \) into days: \[ \frac{40}{3} = 13 \frac{1}{3} \text{ days} \] ### Final Answer A leaves after \( 13 \frac{1}{3} \) days. ---
Promotional Banner

Topper's Solved these Questions

  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE BASE LEVEL QUESTION|68 Videos
  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE HIGHER SKILL LEVEL QUESTION|16 Videos
  • VOLUME AND SURFACE AREA

    ARIHANT SSC|Exercise FAST TRACK PRACTICE|111 Videos
  • WORK AND WAGES

    ARIHANT SSC|Exercise EXERCISE (HIGHER SKILL LEVEL QUESTIONS)|7 Videos

Similar Questions

Explore conceptually related problems

A and B can do a piece of work in 60 days and 75 days, respectively. Both begin together but after a certain time A leaves off . In such case B finishes the remaining work in 30 days . After how many days did A leave ?

A and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?

A and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?

A and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave

A and B can do a piece of work in 45 and 40 days respectively.They began the work together but A leaves after some days and B finished the remaining work in 23 days.After how many days did A leave?

A and B can do a job in 15 days and 10 days, respectively. They began the work together but A leaves after some days and B finished the remaining job in 5 days. After how many days did A leave?

A and B can do a piece of work in 28 and 35 days respectively.They began to work together but A leaves after some time and B completed the remaining work in 17 days. After how many days did A leave? 7(5)/(9) days b. 8) days c.9backslash days d.14(2)/(5) days

ARIHANT SSC-WORK AND TIME -EXERCISE HIGHER SKILL LEVEL QUESTION
  1. A and B can do a piece of work in 40 days and 50 days , respectively....

    Text Solution

    |

  2. A and B can complete a work in 12 days and 18 days, respectively. A be...

    Text Solution

    |

  3. In a factory, there are equal number of women and children. Women work...

    Text Solution

    |

  4. 3 women and 18 children together take 2 days to complete a piece of wo...

    Text Solution

    |

  5. A contractor undertook to finish a certain work in 124 days and employ...

    Text Solution

    |

  6. A contract is to be completed in 92 days and 234 men set to work , eac...

    Text Solution

    |

  7. A, B and C can do a piece of work in 16, 32 and 48 days, respectively....

    Text Solution

    |

  8. Reshmi can do a piece of work in 16 days. Ravina can do the same work ...

    Text Solution

    |

  9. A contract is to be completed in 50 days and 105 men were set to work,...

    Text Solution

    |

  10. A can build up a structure in 8 days and B can break it in 3 days. A h...

    Text Solution

    |

  11. A, B and C can do piece of work in 18,24 and 36 days respectively . Th...

    Text Solution

    |

  12. 6 men can complete a piece of work in 12 days, 8 women can complete...

    Text Solution

    |

  13. A can complete a work in 20 days and B in 30 days. A worked alone for ...

    Text Solution

    |

  14. A and B each working alone can do a work in 15days and 25 days , respe...

    Text Solution

    |

  15. A and B can do piece of work in 9 days and 18 days , respectively. As ...

    Text Solution

    |

  16. Consider the following diagrams x men, working at constant speed, do a...

    Text Solution

    |

  17. A , B and C can do a piece of work individually in 8 , 12 and 15 days ...

    Text Solution

    |