Home
Class 14
MATHS
In a factory, there are equal number of ...

In a factory, there are equal number of women and children. Women work for 6 h a day and children for 4 h a day. During festival time, the work load goes up by 50%. The government rule does not allow children to work for more than 6h a day . If they are equally efficient and the extra work is done by women , then extra hours of work put in by women everday are

A

5

B

3

C

4

D

9

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will follow the reasoning laid out in the video transcript while providing a clearer structure. ### Step-by-Step Solution: 1. **Understanding the Work Hours:** - Women work for 6 hours a day. - Children work for 4 hours a day. - There are equal numbers of women and children in the factory. 2. **Calculating the Workload Increase:** - The workload increases by 50% during festival time. - Let's denote the original workload as \( W \). Therefore, the new workload becomes: \[ W' = W + 0.5W = 1.5W \] 3. **Work Done by Women and Children:** - The work done by women in one day is: \[ W_w = \text{Number of Women} \times 6 \text{ hours} \] - The work done by children in one day is: \[ W_c = \text{Number of Children} \times 4 \text{ hours} \] - Since the number of women is equal to the number of children, we can denote the number of women and children as \( N \). Thus: \[ W_w = N \times 6 \] \[ W_c = N \times 4 \] 4. **Total Work Done by Women and Children:** - The total work done by both women and children in one day is: \[ W_{total} = W_w + W_c = N \times 6 + N \times 4 = N \times 10 \] 5. **Setting Up the Equation for Increased Workload:** - The new workload \( W' \) must be handled by the women and children. Since children cannot work more than 6 hours a day, they will work the maximum allowed: \[ W_c' = N \times 6 \] - The remaining workload must be handled by women: \[ W' = 1.5W = N \times 6 + \text{Extra work by women} \] 6. **Expressing the Original Workload:** - The original workload \( W \) can be expressed as: \[ W = N \times 10 \] - Therefore, the increased workload becomes: \[ W' = 1.5(N \times 10) = N \times 15 \] 7. **Setting Up the Final Equation:** - Now we can set up the equation: \[ N \times 15 = N \times 6 + \text{Extra work by women} \] - Let \( n \) be the extra hours worked by women: \[ N \times 15 = N \times 6 + n \] 8. **Solving for Extra Work:** - Rearranging the equation gives: \[ n = N \times 15 - N \times 6 = N \times (15 - 6) = N \times 9 \] 9. **Finding the Value of \( n \):** - Since \( N \) is a common factor, we can conclude that the extra hours of work put in by women every day is: \[ n = 3 \text{ hours} \] ### Final Answer: The extra hours of work put in by women every day are **3 hours**. ---
Promotional Banner

Topper's Solved these Questions

  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE BASE LEVEL QUESTION|68 Videos
  • VOLUME AND SURFACE AREA

    ARIHANT SSC|Exercise FAST TRACK PRACTICE|111 Videos
  • WORK AND WAGES

    ARIHANT SSC|Exercise EXERCISE (HIGHER SKILL LEVEL QUESTIONS)|7 Videos

Similar Questions

Explore conceptually related problems

Three men, four women and six children can complete a work in seven days. A woman does double the work a man does and a child does half the work a man does. How many women alone can complete this work in 7 days?

In a unit time, the work done by 3 men is equal to the work done by 6 women. The ratio of work done by a man to that of a woman is ………………

In a unit time, the work done by 3 men is equal to the work done by 6 women. The ratio of work done by a man to that of a woman is ………………

In a unit time, the work done by 3 men and 5 women is equal to the work done by 2 men and 7 women. The work done by one man is equal to the work done by ……………… women.

ARIHANT SSC-WORK AND TIME -EXERCISE HIGHER SKILL LEVEL QUESTION
  1. A and B can complete a work in 12 days and 18 days, respectively. A be...

    Text Solution

    |

  2. In a factory, there are equal number of women and children. Women work...

    Text Solution

    |

  3. 3 women and 18 children together take 2 days to complete a piece of wo...

    Text Solution

    |

  4. A contractor undertook to finish a certain work in 124 days and employ...

    Text Solution

    |

  5. A contract is to be completed in 92 days and 234 men set to work , eac...

    Text Solution

    |

  6. A, B and C can do a piece of work in 16, 32 and 48 days, respectively....

    Text Solution

    |

  7. Reshmi can do a piece of work in 16 days. Ravina can do the same work ...

    Text Solution

    |

  8. A contract is to be completed in 50 days and 105 men were set to work,...

    Text Solution

    |

  9. A can build up a structure in 8 days and B can break it in 3 days. A h...

    Text Solution

    |

  10. A, B and C can do piece of work in 18,24 and 36 days respectively . Th...

    Text Solution

    |

  11. 6 men can complete a piece of work in 12 days, 8 women can complete...

    Text Solution

    |

  12. A can complete a work in 20 days and B in 30 days. A worked alone for ...

    Text Solution

    |

  13. A and B each working alone can do a work in 15days and 25 days , respe...

    Text Solution

    |

  14. A and B can do piece of work in 9 days and 18 days , respectively. As ...

    Text Solution

    |

  15. Consider the following diagrams x men, working at constant speed, do a...

    Text Solution

    |

  16. A , B and C can do a piece of work individually in 8 , 12 and 15 days ...

    Text Solution

    |