Home
Class 14
MATHS
A, B and C can do a piece of work in 16,...

A, B and C can do a piece of work in 16, 32 and 48 days, respectively. They all begin together. A work continously till it is finished , C leaves the work 2 days before its completion and B leaves the work 1 day before its completion . In what time is the work finished ?

A

10 days

B

20 days

C

`9 4/11 days`

D

30 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we will first determine the work done by A, B, and C in one day, and then calculate how long it takes for them to finish the work given the conditions stated. ### Step 1: Calculate the work done by A, B, and C in one day. - A can complete the work in 16 days, so the work done by A in one day is: \[ \text{Work done by A in 1 day} = \frac{1}{16} \] - B can complete the work in 32 days, so the work done by B in one day is: \[ \text{Work done by B in 1 day} = \frac{1}{32} \] - C can complete the work in 48 days, so the work done by C in one day is: \[ \text{Work done by C in 1 day} = \frac{1}{48} \] ### Step 2: Calculate the total work done by A, B, and C together in one day. To find the total work done by A, B, and C in one day, we add their individual contributions: \[ \text{Total work done in 1 day} = \frac{1}{16} + \frac{1}{32} + \frac{1}{48} \] To add these fractions, we need a common denominator. The least common multiple (LCM) of 16, 32, and 48 is 96. Converting each fraction: \[ \frac{1}{16} = \frac{6}{96}, \quad \frac{1}{32} = \frac{3}{96}, \quad \frac{1}{48} = \frac{2}{96} \] Now, adding them: \[ \text{Total work done in 1 day} = \frac{6}{96} + \frac{3}{96} + \frac{2}{96} = \frac{11}{96} \] ### Step 3: Let the total number of days taken to finish the work be \( x \). Since A works continuously until the end, and C leaves 2 days before the work is finished while B leaves 1 day before, we can set up the equation based on the work done. - A works for \( x \) days. - B works for \( x - 1 \) days. - C works for \( x - 2 \) days. The total work done can be expressed as: \[ \text{Work done by A} + \text{Work done by B} + \text{Work done by C} = 1 \] Substituting the work done: \[ \frac{x}{16} + \frac{x - 1}{32} + \frac{x - 2}{48} = 1 \] ### Step 4: Solve the equation. To solve this equation, we will first find a common denominator, which is 96: \[ \frac{6x}{96} + \frac{3(x - 1)}{96} + \frac{2(x - 2)}{96} = 1 \] Combining the fractions: \[ \frac{6x + 3(x - 1) + 2(x - 2)}{96} = 1 \] Expanding: \[ 6x + 3x - 3 + 2x - 4 = 96 \] \[ 11x - 7 = 96 \] \[ 11x = 103 \] \[ x = \frac{103}{11} \approx 9.36 \] ### Step 5: Calculate the time taken to finish the work. Since \( x \) represents the total days taken to finish the work, we round it to the nearest whole number. Thus, the work is finished in approximately 9 days. ### Final Answer: The work is finished in approximately **9 days**. ---
Promotional Banner

Topper's Solved these Questions

  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE BASE LEVEL QUESTION|68 Videos
  • VOLUME AND SURFACE AREA

    ARIHANT SSC|Exercise FAST TRACK PRACTICE|111 Videos
  • WORK AND WAGES

    ARIHANT SSC|Exercise EXERCISE (HIGHER SKILL LEVEL QUESTIONS)|7 Videos

Similar Questions

Explore conceptually related problems

A, B and C can do a work in 8, 16 and 24 days respectively. They all begin together. A continues to work till it is finished, C leaving off 2 days and B one day before its completion. In what time is the work finished?

A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

A, B and C can complete a piec of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work in completed ?

A, B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. They started working together. B left the work after working 3 days and C left the work 3 days before completion of the work. In how many days work will be finished?

A, B and C can do a piece of work in 20, 24 and 30 days, respectively. They undertook to do the piece of work for Rs. 5400. They begin the work together but B left 2 days before the completion of work and c left 5 days before the completion of work. The share of A from the assured money is

ARIHANT SSC-WORK AND TIME -EXERCISE HIGHER SKILL LEVEL QUESTION
  1. A and B can complete a work in 12 days and 18 days, respectively. A be...

    Text Solution

    |

  2. In a factory, there are equal number of women and children. Women work...

    Text Solution

    |

  3. 3 women and 18 children together take 2 days to complete a piece of wo...

    Text Solution

    |

  4. A contractor undertook to finish a certain work in 124 days and employ...

    Text Solution

    |

  5. A contract is to be completed in 92 days and 234 men set to work , eac...

    Text Solution

    |

  6. A, B and C can do a piece of work in 16, 32 and 48 days, respectively....

    Text Solution

    |

  7. Reshmi can do a piece of work in 16 days. Ravina can do the same work ...

    Text Solution

    |

  8. A contract is to be completed in 50 days and 105 men were set to work,...

    Text Solution

    |

  9. A can build up a structure in 8 days and B can break it in 3 days. A h...

    Text Solution

    |

  10. A, B and C can do piece of work in 18,24 and 36 days respectively . Th...

    Text Solution

    |

  11. 6 men can complete a piece of work in 12 days, 8 women can complete...

    Text Solution

    |

  12. A can complete a work in 20 days and B in 30 days. A worked alone for ...

    Text Solution

    |

  13. A and B each working alone can do a work in 15days and 25 days , respe...

    Text Solution

    |

  14. A and B can do piece of work in 9 days and 18 days , respectively. As ...

    Text Solution

    |

  15. Consider the following diagrams x men, working at constant speed, do a...

    Text Solution

    |

  16. A , B and C can do a piece of work individually in 8 , 12 and 15 days ...

    Text Solution

    |