Home
Class 14
MATHS
Reshmi can do a piece of work in 16 days...

Reshmi can do a piece of work in 16 days. Ravina can do the same work in `12 (4)/(5)`days , while gitika can do it in 32 days. All of them started to work together but reshmi leaves after 4 days. Ravina leaves the job 3 days before the completion of the work . how long would the work last ?

A

9 days

B

6 days

C

16 days

D

5 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we will follow these steps: ### Step 1: Determine the work done by each person in one day. - Reshmi can complete the work in 16 days. Therefore, her work rate is: \[ \text{Reshmi's work rate} = \frac{1 \text{ work}}{16 \text{ days}} = \frac{1}{16} \text{ work/day} \] - Ravina can complete the work in \(12 \frac{4}{5}\) days. First, convert \(12 \frac{4}{5}\) into an improper fraction: \[ 12 \frac{4}{5} = \frac{12 \times 5 + 4}{5} = \frac{60 + 4}{5} = \frac{64}{5} \text{ days} \] Therefore, her work rate is: \[ \text{Ravina's work rate} = \frac{1 \text{ work}}{\frac{64}{5} \text{ days}} = \frac{5}{64} \text{ work/day} \] - Gitika can complete the work in 32 days. Therefore, her work rate is: \[ \text{Gitika's work rate} = \frac{1 \text{ work}}{32 \text{ days}} = \frac{1}{32} \text{ work/day} \] ### Step 2: Calculate the total work done by all three in one day. Now we will add their work rates together to find the total work done by all three in one day: \[ \text{Total work rate} = \text{Reshmi's work rate} + \text{Ravina's work rate} + \text{Gitika's work rate} \] \[ = \frac{1}{16} + \frac{5}{64} + \frac{1}{32} \] To add these fractions, we need a common denominator. The least common multiple (LCM) of 16, 64, and 32 is 64. We convert each fraction: \[ \frac{1}{16} = \frac{4}{64}, \quad \frac{5}{64} = \frac{5}{64}, \quad \frac{1}{32} = \frac{2}{64} \] Now, adding them together: \[ \text{Total work rate} = \frac{4}{64} + \frac{5}{64} + \frac{2}{64} = \frac{11}{64} \text{ work/day} \] ### Step 3: Calculate the work done in the first 4 days. In the first 4 days, the total work done by all three is: \[ \text{Work done in 4 days} = 4 \times \frac{11}{64} = \frac{44}{64} = \frac{11}{16} \text{ work} \] ### Step 4: Calculate the remaining work. The total work is 1 (the whole work), so the remaining work after 4 days is: \[ \text{Remaining work} = 1 - \frac{11}{16} = \frac{5}{16} \text{ work} \] ### Step 5: Determine how many days Ravina and Gitika work. Ravina leaves 3 days before the completion of the work. Let \(X\) be the total number of days the work lasts. Therefore, Ravina works for \(X - 3\) days. Since Reshmi leaves after 4 days, only Ravina and Gitika work for the remaining days. The work done by Ravina and Gitika in one day is: \[ \text{Ravina's work rate} + \text{Gitika's work rate} = \frac{5}{64} + \frac{1}{32} = \frac{5}{64} + \frac{2}{64} = \frac{7}{64} \text{ work/day} \] ### Step 6: Set up the equation for the remaining work. The remaining work is done by Ravina and Gitika: \[ \text{Remaining work} = \text{Work rate} \times \text{Days worked} \] \[ \frac{5}{16} = \frac{7}{64} \times (X - 4 - 3) \] \[ \frac{5}{16} = \frac{7}{64} \times (X - 7) \] ### Step 7: Solve for \(X\). Cross-multiply to solve for \(X\): \[ 5 \times 64 = 7 \times 16 \times (X - 7) \] \[ 320 = 112(X - 7) \] \[ 320 = 112X - 784 \] \[ 112X = 320 + 784 \] \[ 112X = 1104 \] \[ X = \frac{1104}{112} = 9.857 \text{ days} \approx 10 \text{ days} \] ### Final Answer: The work lasts approximately **10 days**. ---
Promotional Banner

Topper's Solved these Questions

  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE BASE LEVEL QUESTION|68 Videos
  • VOLUME AND SURFACE AREA

    ARIHANT SSC|Exercise FAST TRACK PRACTICE|111 Videos
  • WORK AND WAGES

    ARIHANT SSC|Exercise EXERCISE (HIGHER SKILL LEVEL QUESTIONS)|7 Videos

Similar Questions

Explore conceptually related problems

A can complete a work in 16 days, B in 12 days and C in l5 days. All of them began the work together, but A had to leave the work after 2 days of the start and B 3 days before the completion of the work. How long did the work last?

A can do a piece of work in 8 days, B can do it in 16 days, while C can do it in 80 days. In how many days they can complete the whole work, working together?

A can do a piece of work in 9 days and B can do the same in 12 days. In how days can the work be completed if A and B work together?

A can do a piece of work in 16 days and B can do the same work in 20 days.In how many days can they do the same work,working together?

A and B together can do a piece of work in 12 days; B and C can do it in 20 days while C and A can do it in 15 days. A, B and C all working together can do it in

Raju can do a piece of work in 10 days, Vicky in 12 days and Tinku in 15 days. They all start the work together, but Raju leaves after 2 days and Vicky leaves 3 days before the work is completed. In how many days is the work completed?

Rajan can do a piece of work in 24 days while Amit can do it in 30 days. In how many days can they complete it they work together?

ARIHANT SSC-WORK AND TIME -EXERCISE HIGHER SKILL LEVEL QUESTION
  1. A and B can complete a work in 12 days and 18 days, respectively. A be...

    Text Solution

    |

  2. In a factory, there are equal number of women and children. Women work...

    Text Solution

    |

  3. 3 women and 18 children together take 2 days to complete a piece of wo...

    Text Solution

    |

  4. A contractor undertook to finish a certain work in 124 days and employ...

    Text Solution

    |

  5. A contract is to be completed in 92 days and 234 men set to work , eac...

    Text Solution

    |

  6. A, B and C can do a piece of work in 16, 32 and 48 days, respectively....

    Text Solution

    |

  7. Reshmi can do a piece of work in 16 days. Ravina can do the same work ...

    Text Solution

    |

  8. A contract is to be completed in 50 days and 105 men were set to work,...

    Text Solution

    |

  9. A can build up a structure in 8 days and B can break it in 3 days. A h...

    Text Solution

    |

  10. A, B and C can do piece of work in 18,24 and 36 days respectively . Th...

    Text Solution

    |

  11. 6 men can complete a piece of work in 12 days, 8 women can complete...

    Text Solution

    |

  12. A can complete a work in 20 days and B in 30 days. A worked alone for ...

    Text Solution

    |

  13. A and B each working alone can do a work in 15days and 25 days , respe...

    Text Solution

    |

  14. A and B can do piece of work in 9 days and 18 days , respectively. As ...

    Text Solution

    |

  15. Consider the following diagrams x men, working at constant speed, do a...

    Text Solution

    |

  16. A , B and C can do a piece of work individually in 8 , 12 and 15 days ...

    Text Solution

    |