Home
Class 14
MATHS
A can complete a work in 20 days and B i...

A can complete a work in 20 days and B in 30 days. A worked alone for 4 days and then B completed the remaining work along with C in 18 days . In how many days can C working alone complete the work ?

A

12

B

68

C

72

D

90

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we need to determine how much work A, B, and C can do individually and then find out how long C would take to complete the entire work alone. ### Step 1: Determine the work done by A in 4 days. A can complete the work in 20 days. Therefore, the work done by A in one day is: \[ \text{Work done by A in 1 day} = \frac{1}{20} \] In 4 days, A will complete: \[ \text{Work done by A in 4 days} = 4 \times \frac{1}{20} = \frac{4}{20} = \frac{1}{5} \] ### Step 2: Calculate the remaining work after A's contribution. The total work can be considered as 1 (the whole work). After A has completed \(\frac{1}{5}\) of the work, the remaining work is: \[ \text{Remaining work} = 1 - \frac{1}{5} = \frac{4}{5} \] ### Step 3: Determine the combined work rate of B and C. B can complete the work in 30 days, so the work done by B in one day is: \[ \text{Work done by B in 1 day} = \frac{1}{30} \] Let C's work rate be \(\frac{1}{C}\) (where C can complete the work in C days). The combined work done by B and C in one day is: \[ \text{Work done by B and C in 1 day} = \frac{1}{30} + \frac{1}{C} \] ### Step 4: Calculate the work done by B and C together in 18 days. In 18 days, B and C together complete the remaining work of \(\frac{4}{5}\): \[ \text{Work done by B and C in 18 days} = 18 \left( \frac{1}{30} + \frac{1}{C} \right) = \frac{4}{5} \] ### Step 5: Set up the equation. Now we can set up the equation: \[ 18 \left( \frac{1}{30} + \frac{1}{C} \right) = \frac{4}{5} \] ### Step 6: Solve for C. First, simplify the left side: \[ \frac{18}{30} + \frac{18}{C} = \frac{4}{5} \] This simplifies to: \[ \frac{3}{5} + \frac{18}{C} = \frac{4}{5} \] Subtract \(\frac{3}{5}\) from both sides: \[ \frac{18}{C} = \frac{4}{5} - \frac{3}{5} = \frac{1}{5} \] Now, cross-multiply to solve for C: \[ 18 \cdot 5 = 1 \cdot C \implies C = 90 \] ### Conclusion: C can complete the work alone in 90 days.
Promotional Banner

Topper's Solved these Questions

  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE BASE LEVEL QUESTION|68 Videos
  • VOLUME AND SURFACE AREA

    ARIHANT SSC|Exercise FAST TRACK PRACTICE|111 Videos
  • WORK AND WAGES

    ARIHANT SSC|Exercise EXERCISE (HIGHER SKILL LEVEL QUESTIONS)|7 Videos

Similar Questions

Explore conceptually related problems

A can complete a work in 20 days and B, in 30 days. A worked alone for 4 days and B completed the remaining work along with C in 18 days. In how many days 'C’ can working, alone complete the work? A किसी काम को 20 दिन में समाप्त कर सकता है, और B, 30 दिन में, A अकेला 4 दिन तक काम करता है, और शेष कार्य B, C के साथ मिलकर 18 दिन में करता है। C अकेला उस काम को कितने दिन में कर सकता है।

A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?

A and B can do a piece of work in 12 days and B and C can do the same piece of work in 16 days.A work for 5 days and B work for 7 days and C complete the remaining work in 13 days then in how many days C would complete the same work?

(A + B) can do a piece of work in 12 days. (B + C) can do same work in 6(2)/(3) days. A work for 3 days, B works for 4 days and C completed the remaining work in 7 days. In how many days will A, B and C do this work alone ?

A and B can finish a work together in 12 days, and B and C together in 16 days. If A alone works for 5 days and then B alone continues for 7 days, then remaining work is done by C in 13 days. In how many days can C alone finish the complete work?

ARIHANT SSC-WORK AND TIME -EXERCISE HIGHER SKILL LEVEL QUESTION
  1. A and B can complete a work in 12 days and 18 days, respectively. A be...

    Text Solution

    |

  2. In a factory, there are equal number of women and children. Women work...

    Text Solution

    |

  3. 3 women and 18 children together take 2 days to complete a piece of wo...

    Text Solution

    |

  4. A contractor undertook to finish a certain work in 124 days and employ...

    Text Solution

    |

  5. A contract is to be completed in 92 days and 234 men set to work , eac...

    Text Solution

    |

  6. A, B and C can do a piece of work in 16, 32 and 48 days, respectively....

    Text Solution

    |

  7. Reshmi can do a piece of work in 16 days. Ravina can do the same work ...

    Text Solution

    |

  8. A contract is to be completed in 50 days and 105 men were set to work,...

    Text Solution

    |

  9. A can build up a structure in 8 days and B can break it in 3 days. A h...

    Text Solution

    |

  10. A, B and C can do piece of work in 18,24 and 36 days respectively . Th...

    Text Solution

    |

  11. 6 men can complete a piece of work in 12 days, 8 women can complete...

    Text Solution

    |

  12. A can complete a work in 20 days and B in 30 days. A worked alone for ...

    Text Solution

    |

  13. A and B each working alone can do a work in 15days and 25 days , respe...

    Text Solution

    |

  14. A and B can do piece of work in 9 days and 18 days , respectively. As ...

    Text Solution

    |

  15. Consider the following diagrams x men, working at constant speed, do a...

    Text Solution

    |

  16. A , B and C can do a piece of work individually in 8 , 12 and 15 days ...

    Text Solution

    |