A is twice as good a workman as B and is...

A is twice as good a workman as B and is therefore able to finish a piece of work in 30 days less than B. In how many days they can complete the whole work, working together?

Text Solution

Verified by Experts

The correct Answer is:
20 days
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    ARIHANT SSC|Exercise EXERCISE(LEVEL 1)|100 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|55 Videos
  • THEORY OF EQUATIONS

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|20 Videos
  • TIME, SPEED AND DISTANCE

    ARIHANT SSC|Exercise SPEED TEST (TSD)|10 Videos

Similar Questions

Explore conceptually related problems

A is thrice as good a workman as B and is, therefore, able to finish a piece of work in 60 days less than B. The time (in days) in which they can do it working together is

A is thrice as good a workman as B and therefore is able to finish a job in 30 days less than B. How many days will they take to finish the job working together?

A is thrice as good a workman as B and therefore is able to finish a job in 40 days less than B. Working together, they can do it in

A is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can B alone finish the work?

A is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can A alone finish the work?

A is twice as good a workman as B and together they finish a piece of work in 20 days. In how many days will A alone finish the work?

A is twice as good a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work?