A person has undertaken a construction job. The probabilities are `0.80` that there will be a strike, `0.70` that the construction job will be completed on time if there is no strike, and `0.4` that the construction job will be completed on time if there is a strike. Determine the probability that the construction job will be completed on time.

Text Solution

AI Generated Solution

To determine the probability that the construction job will be completed on time, we will use the law of total probability. Here are the steps: ### Step 1: Define the Events Let: - \( A \): the event that the construction job will be completed on time. - \( B \): the event that there will be a strike. ### Step 2: Identify Given Probabilities ...
Promotional Banner

Topper's Solved these Questions

  • PROBABILITY II

    CENGAGE ENGLISH|Exercise SOLVED EXAMPLES|21 Videos
  • PROBABILITY II

    CENGAGE ENGLISH|Exercise CONCEPT APPCICATION EXERCISE 14.1|5 Videos
  • PROBABILITY I

    CENGAGE ENGLISH|Exercise JEE Advanced|7 Videos
  • PROGRESSION AND SERIES

    CENGAGE ENGLISH|Exercise ARCHIVES (MATRIX MATCH TYPE )|1 Videos

Similar Questions

Explore conceptually related problems

A person has undertaken a construction job. The probabilities are 0.65 that there will be strike. 0.80 that the construction job will be completed on time if there is no strike, and 0.32 that the construction job will be completed on time if ther

A person has undertaken a construction job. The probablities are 0.65 that will be strike, 0.80 that the construction job will becompleted on time if there is no strike, and 0.32 that the construction job will be completed on time if there is a strike. Then the probability that the construction job will be completed on time is

A man takes the contract of construction work. The probability is 0.30, if there will be no strike. The probability that the construct work will be completed on time are 0.8 and 0.3 in cases of no strike and in case strike respectively. Find the probability that the construction work will be completed in time.

If the probability that Mike will miss at least one of ten jobs assigned to him is 0.55, then what is the probability that he will do all ten jobs?

The probability that a man will hit a target in shooting practise is 0.3 . If he shoots 10 times, the probability that he hits the target , is

The coefficients a,b and c of the quadratic equation, ax2+bx+c = 0 are obtained by throwing a dice three times. The probability that this equation has equal roots is:

The probability of happening of an event in a trial is 0.5. The probability of happening of the event atlest once if the experiment is repeated 3 times is

The probability of happening of an event is 0.6 for one experiment. In three such experiments, find the probability of happening the event at least one time.

The probability of a man hitting a target is 0.25. He shoots 7 times. What is the probability of his hitting at least twice?

The probability of a man hitting a target is 0.25. He shoots 7 times. What is the probability of his hitting at least twice?