Home
Class 8
MATHS
Fifteen men can complete a piece of work...

Fifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we can use the concept of work done, which is calculated as the product of the number of men, the number of days, and the number of hours worked per day. ### Step 1: Calculate the total work done by 15 men in 10 days working 8 hours per day. Total work (W1) = Number of men (M1) × Number of days (D1) × Hours per day (T1) Given: - M1 = 15 men - D1 = 10 days - T1 = 8 hours/day \[ W1 = 15 \times 10 \times 8 = 1200 \text{ man-hours} \] ### Step 2: Determine the total work required for double the work. Since we need to complete double the work, we have: \[ W2 = 2 \times W1 = 2 \times 1200 = 2400 \text{ man-hours} \] ### Step 3: Set up the equation for the new scenario. We need to find out how many men (M2) are required to complete this work in 25 days working 6 hours per day. Total work (W2) can also be expressed as: \[ W2 = M2 \times D2 \times T2 \] Where: - D2 = 25 days - T2 = 6 hours/day ### Step 4: Substitute the values into the equation. \[ 2400 = M2 \times 25 \times 6 \] ### Step 5: Solve for M2. First, calculate \(25 \times 6\): \[ 25 \times 6 = 150 \] Now, substitute this back into the equation: \[ 2400 = M2 \times 150 \] To find M2, divide both sides by 150: \[ M2 = \frac{2400}{150} = 16 \] ### Conclusion: Therefore, **16 men** are required to complete double the work in 25 days working 6 hours per day. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK, PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise CONCEPT APPLICATION (LEVEL-1)|33 Videos
  • TIME AND WORK, PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise CONCEPT APPLICATION (LEVEL-2)|20 Videos
  • TIME AND WORK, PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise Short Answer Type Questions|15 Videos
  • TIME AND WORK PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise CONCEPT APPLICATION (LEVEL-3)|7 Videos

Similar Questions

Explore conceptually related problems

If 25 men can do a piece of work in 36 days working 10 hours a day, then how many men are required to complete the work working 6 hours a day in 20 days?

12 men can complete a work in 30 days by working 9 hours a day. What is the number of men required to complete 10 times of this work in 24 days by working 5 hours a day ?

7 men can complete a plece of work in 12 days. How many additional men will be required to complete double the work in 8 days ?

If 20 men take 15 days to complete a certain amount of work working at 10 hours per day, then how many more men are required to complete twice the previous work in 10 days working at 12 hours a day?